Permit Details

Status:
Final
Type:
COMMERCIAL ALTERATION
Address NEW:
278 E CONGRESS ST
Apply Date:
05/10/2010
Applicant:
N/A
Description:
TI:RESTAURANT
Contractors:
  • CUTSHAW YEAGER CONSTRUCTION LLC

Permit Reviews

Permit Number - T10CM01281
Permit Status: Final
Permit Description: TI:RESTAURANT
Start Date Submittal Complete Date Status  
04/20/2011 REVISION - - 3RD 05/04/2011 COMPLETED Review Details
04/29/2011 REVISION - - 4TH 05/19/2011 COMPLETED Review Details
05/10/2010 PLANS OK TO SUBMIT - COMM 05/10/2010 COMPLETED Review Details
05/10/2010 COMMERCIAL TI 07/07/2010 COMPLETED Review Details
05/19/2011 REVISION - - 4TH 06/28/2011 COMPLETED Review Details
06/28/2011 REVISION - - 5TH 07/11/2011 ACTIVE Review Details
07/07/2010 RESUBMITTAL - TI ALL 08/05/2010 COMPLETED Review Details
08/05/2010 RESUBMITTAL - TI ALL 08/17/2010 COMPLETED Review Details
08/17/2010 RESUBMITTAL 10/04/2010 COMPLETED Review Details
12/15/2010 REVISION - - 1ST 12/15/2010 COMPLETED Review Details
12/30/2010 REVISION - - 2ND 05/04/2011 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10CM01281
Permit Status: Final
Permit Description: TI:RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
05/10/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T10CM01281
Permit Description: TI:RESTAURANT
Total Completed Inspections - 51
Date Description Inspector Results Comments
10/05/2010 STEM WALL/RETAINING WALL LHANLY Approved
10/05/2010 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved
10/05/2010 ROOF NAILING LHANLY Approved
10/05/2010 ROOF NAILING LHANLY Approved
10/07/2010 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection :*
10/12/2010 PLUMBING - PRE SLAB LHANLY Approved OK AT BATHROOM GROUPS
10/12/2010 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved
10/18/2010 BUILDING PRE-SLAB LHANLY Approved EXTERIOR RAMPS AND STEPS OK TO PLACE
10/28/2010 PLUMBING - ROUGH, SOIL LHANLY Approved SUMP TANK INSTALLATION OK FOR BACKFILL. STILL NEED TO SEE DISCHARGE PIPE INSTALLATION.

DO NOT COVER VENT FROM INTERCEPTOR UNTIL IT HAS BEEN TESTED AND INSPECTED
11/19/2010 ELECTRIC - UFER LHANLY Approved
11/19/2010 STUCCO MESH LHANLY Approved
12/09/2010 FRAMING LHANLY Approved ELEVATOR FRAME OK
12/21/2010 ELECTRIC - UNDERGROUND LHANLY Approved CONDUIT FOR PARKING LOT LIGHTS OK
12/30/2010 BUILDING - PROGRESS LHANLY Approved ELEVATOR STUCCO OK. STEEL EYEBROWS AT CORNERS OK. LIGHT POLE BASES OK.
04/01/2011 ELECTRIC - CABLE DROP LHANLY Approved OK TO CLEAR CABLE DROP TO SWITCH GEAR.
04/19/2011 TEP CLEARANCE - PM JWEATHER Approved ECO CLEARED FOR "HOUSE PANEL" PER L. HANLY
07/11/2011 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED FOR 276 E. CONGRESS ST; PER L. HANLY
07/11/2011 ELECTRIC - OUTDOOR LIGHTING LHANLY Approved
07/11/2011 ELECTRIC - CONSTRUCTION POWER LHANLY Approved
09/26/2011 MECHANICAL - FINAL LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 MECHANICAL - PROGRESS LHANLY Approved
09/26/2011 MECHANICAL - HOODS LHANLY Approved
09/26/2011 MECHANICAL - ABOVE CEILING LHANLY Approved
09/26/2011 MECHANICAL - INTERMEDIATE LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 PLUMBING - FINAL LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 PLUMBING - PROGRESS LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 PLUMBING - SEWER HCS CONNECT LHANLY Approved
09/26/2011 PLUMBING - GAS PRESS TEST FNL LHANLY Approved
09/26/2011 PLUMBING - GAS PRESSURE TEST LHANLY Approved
09/26/2011 PLUMBING - YARD WTR LINE/TEST LHANLY Approved
09/26/2011 PLUMBING - ROOF DRAINS LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 PLUMBING - ABOVE CEILING LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 PLUMBING - INTERMEDIATE LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 OUTDOOR LIGHTING FINAL LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 ELECTRIC - FINAL LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 ELECTRIC - PROGRESS LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 ELECTRIC - TEMPORARY SERVICE LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 ELECTRIC - ABOVE CEILING LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 ELECTRIC - INTERMEDIATE LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 BUILDING - FINAL LHANLY Approved SEE NOTICE FOR REDUCTION OF SCOPE ALL WORK COMPLETED TO DATE MEETS CODE AND PLAN DOCUMENTS. ALL FUTURE WORK TO BE DOCUMENTED IN NEW PLAN SETS FOR NEW ADDRESSES.
09/26/2011 BUILDING - FINAL LHANLY Approved WORK COMPLETED TO DATE MEETS CODE. PLANS FOR LARGE SPORTS BAR HAVE BEEN SCRAPPED SO THIS ACTIVITY ONLY COVERS BASIC STRUCTURAL AND INFRASTRUCTURE.
09/26/2011 SHEET ROCK NAILING LHANLY Approved
09/26/2011 U VALUE FOR WINDOW LHANLY Approved
09/26/2011 BUILDING ABOVE CEILING LHANLY Approved WORK COMPLETED TO DATE MEETS CODE. THIS PLAN TO BE OVER-WRITTEN BY NEW ACTIVITY
10/06/2011 FIRE - ALARM FINAL MBROWN Approved
10/06/2011 FIRE - KITCHEN EXH HOOD FINAL MBROWN Approved
10/06/2011 FIRE SPKLR - FINAL MBROWN Approved
10/06/2011 FIRE SPKLR - UG, PIPING, HYDRO MBROWN Approved
10/06/2011 FIRE - FINAL MBROWN Approved
12/02/2011 ENGINEERING - FINAL LHANLY Approved
12/02/2011 ZONING - FINAL LHANLY Approved