Permit: T10CM01088
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
5925 E BROADWAY BL #125
Address NEW:
5925 E BROADWAY BL #125
Apply Date:
04/21/2010
Applicant:
N/A
Description:
TI & C OF O: CORPORATE OFFICE
Architects:
- CAPPS, ANTHONY G
Contractors:
- TOFEL CONSTRUCTION
Permit Reviews
Permit Number - T10CM01088
Permit Status: C of o
Permit Description: TI & C OF O: CORPORATE OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/21/2010 | COMMERCIAL TI | 04/27/2010 | COMPLETED |
| 04/27/2010 | COMMERCIAL TI | 04/28/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01088
Permit Status: C of o
Permit Description: TI & C OF O: CORPORATE OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/21/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01088
Permit Description: TI & C OF O: CORPORATE OFFICE
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2010 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 05/20/2010 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/17/2010 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 06/17/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/18/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) FRONT SOFFIT WALLS OK 2) PANEL ROOM AND PANEL WALL FOR OFFICE WALLS OK 3) ALL WALLS IN BLDG OK |
| 06/21/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK AND INSULATE |
| 06/29/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
| 08/04/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 08/05/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/12/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 08/17/2010 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 08/18/2010 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
| 08/19/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 08/27/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 08/27/2010 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/27/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/27/2010 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 08/27/2010 | LANDSCAPE - FINAL | JFEMLING | Approved | Approved |
| 08/27/2010 | NPPO - FINAL | JFEMLING | Approved | Approved |
| 08/31/2010 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
| 08/31/2010 | FIRE - FINAL | DSIWARSKI | Approved | |
| 09/01/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 09/02/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 09/02/2010 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | IVRS - Inspection :* |
| 09/02/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 09/02/2010 | ENGINEERING - FINAL | JFEMLING | Approved | All items complete, approved |
| 09/02/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |