Permit: T10CM00153
Permit Details
Apply Date:
01/20/2010
Applicant:
N/A
Description:
ADDITION:GARAGE W/BATHROOM
Permit Reviews
Permit Number - T10CM00153
Permit Status: Final
Permit Description: ADDITION:GARAGE W/BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2010 | PLANS OK TO SUBMIT - RES | 02/09/2010 | COMPLETED |
| 02/09/2010 | RESIDENTIAL BLDG/WWM | 03/11/2010 | COMPLETED |
| 03/30/2010 | RESUBMITTAL | 04/12/2010 | COMPLETED |
| 04/14/2010 | RESUBMITTAL | 04/26/2010 | COMPLETED |
| 04/26/2010 | RESUBMITTAL | 04/27/2010 | COMPLETED |
| 04/27/2010 | RESUBMITTAL | 04/28/2010 | COMPLETED |
| 06/02/2010 | REVISION - - 1ST | 06/18/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00153
Permit Status: Final
Permit Description: ADDITION:GARAGE W/BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/20/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T10CM00153
Permit Description: ADDITION:GARAGE W/BATHROOM
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/12/2010 | ELECTRIC - UNDERGROUND | DQUINN | Approved | IVRS - Inspection :* |
| 05/13/2010 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 05/17/2010 | PLUMBING - PRE SLAB | RFREIDIN | Approved | IVRS - Inspection :* 0200 VHOL OK 1) OK A UNDER SLAB GROUND TO SUBPANE. |
| 05/17/2010 | BUILDING PRE-SLAB | RFREIDIN | Approved | IVRS - Inspection :* |
| 05/17/2010 | EXCAVATION/LAYOUT REBAR & ZON | RFREIDIN | Approved | IVRS - Inspection :* |
| 06/28/2010 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 07/16/2010 | STUCCO MESH | DQUINN | Approved | |
| 08/04/2010 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | IVRS - Inspection :* |
| 08/04/2010 | BUILDING ABOVE CEILING | DQUINN | Approved | IVRS - Inspection :* |
| 08/04/2010 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 08/04/2010 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 08/04/2010 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 08/18/2010 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* 1) STORAGE PLATFORM AT S.E. CORNER OK'D BY TRUSS ENGINEER |
| 09/21/2010 | PLUMBING - FINAL | DWALKER | Approved | |
| 09/21/2010 | ELECTRIC - FINAL | DWALKER | Approved | |
| 09/21/2010 | CERTIFICATE OF OCCUPANCY | DWALKER | Approved | |
| 09/21/2010 | BUILDING - FINAL | DWALKER | Approved | |
| 09/21/2010 | STEM WALL/RETAINING WALL | DWALKER | Approved | |
| 09/22/2010 | PERMIT FINALED | JWEATHER | Approved |