Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Grading and SWPPP
Apply Date:
07/01/2010
Applicant:
N/A
Description:
GRADING FOR D10-0022
Contractors:
  • WITHERS CONSTRUCTION L C , D L

Permit Reviews

Permit Number - T10BU01053
Permit Status: Final
Permit Description: GRADING FOR D10-0022
Start Date Submittal Complete Date Status  
07/01/2010 PLANS OK TO SUBMIT - GRADING 07/01/2010 COMPLETED Review Details
10/20/2010 RESUBMITTAL - GRADING 10/21/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T10BU01053
Permit Status: Final
Permit Description: GRADING FOR D10-0022
Total Outstanding Activity Conditions - 1
Date Name
07/01/2010 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T10BU01053
Permit Description: GRADING FOR D10-0022
Total Completed Inspections - 12
Date Description Inspector Results Comments
11/03/2010 ENGINEERING PRE-CONSTRUCTION JFEMLING Approved Met with contractor and discussed SWPPP, Water Harvest and grading plans
11/04/2010 STORMWATER INSTALL OF CONTROLS JFEMLING Approved Contruction entrance is installed off of Toole Ave.
11/04/2010 STORMWATER INSTALL OF CONTROLS JFEMLING Approved Straw waddel has been delivered to site but not installed, dirt work underway. I told contractor to install waddel by the end of day.
12/20/2010 STORMWATER FOLLOW-UP INSP JFEMLING Approved Storm controls are in good shape, street sweeper onsite last week cleaning Toole during conc placement.
12/20/2010 GRADING - INTERMEDIATE JFEMLING Approved Contractor continuing to set columns for garage structure, they exposed the existing storm rcp and haved cleared with foundation.
09/06/2011 GRADING - CHECK FOR ACTIVITY JFEMLING Approved Approved
09/06/2011 GRADING - REBAR JFEMLING Approved Approved
09/06/2011 GRADING - TIER REV JFEMLING Approved Approved
09/08/2011 RAINWATER - FINAL JFEMLING Approved Approved
09/08/2011 RAINWATER - INTERMEDIATE JFEMLING Approved Approved
09/08/2011 STORMWATER FINAL INSPECTION JFEMLING Approved Approved
09/08/2011 GRADING - FINAL JFEMLING Approved OK for Temp C of O complete items 3,5,6,7 prior to final C of O.

Documents

File Name Document Type  
None DOCUMENTS VIEW
PERFORMANCE BOND 2010.PDF DOCUMENTS VIEW
BOND RELEASE LETTER 2011.PDF DOCUMENTS VIEW