Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T10BU01053
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/08/2011 | GRADING - INTERMEDIATE | Approved | Approved | |
08/02/2011 | GRADING - INTERMEDIATE | Continued | Inspected storm pipe connection to existing storm MH on congress, told contractor to compact trench as backfilled. | |
07/26/2011 | GRADING - INTERMEDIATE | Continued | Met with contractor to discuss downspout drain from parking garage, wanted to tie into existing storm line. I discussed with Jason Green and we decided it would be best ti tie into an existing storm MH, if not possible then tie into existing storm pipe with a cleanout. I let contractor know, he will try and tie into MH. | |
06/09/2011 | GRADING - INTERMEDIATE | Continued | Work continuing on structure, no real site work at this time. | |
05/13/2011 | GRADING - INTERMEDIATE | Continued | Work continuing on structure, very little site work at this time. | |
04/27/2011 | GRADING - INTERMEDIATE | Continued | Building under construction, no site work at this time. | |
12/20/2010 | GRADING - INTERMEDIATE | Continued | Contractor continuing to set columns for garage structure, they exposed the existing storm rcp and haved cleared with foundation. | |
11/29/2010 | GRADING - INTERMEDIATE | Continued | Contractor placing steel for columns. | |
11/04/2010 | GRADING - INTERMEDIATE | Continued | Earthwork began at site, sidewalk pavers along Congress have been removed. |