Permit: T09CM03166
Permit Details
Apply Date:
12/02/2009
Applicant:
N/A
Description:
DEMO:FRONT:REAR:PORCH:MASTER BEDROOM
Permit Reviews
Permit Number - T09CM03166
Permit Status: Final
Permit Description: DEMO:FRONT:REAR:PORCH:MASTER BEDROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/28/2010 | RESUBMITTAL | 01/28/2010 | ACTIVE |
| 12/02/2009 | PLANS OK TO SUBMIT - RES | 12/10/2009 | COMPLETED |
| 12/11/2009 | RESIDENTIAL BLDG/WWM | 01/13/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM03166
Permit Status: Final
Permit Description: DEMO:FRONT:REAR:PORCH:MASTER BEDROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/02/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM03166
Permit Description: DEMO:FRONT:REAR:PORCH:MASTER BEDROOM
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/01/2010 | ELECTRIC - UFER | DQUINN | Approved | IVRS - Inspection :* |
| 02/01/2010 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 02/04/2010 | STEM WALL/RETAINING WALL | RFREIDIN | Approved | |
| 02/12/2010 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection :* |
| 02/12/2010 | PLUMBING - YARD WTR LINE/TEST | EDURAZO | Approved | IVRS - Inspection :* |
| 02/16/2010 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 03/18/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 03/18/2010 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 04/14/2010 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/14/2010 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 04/14/2010 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 04/14/2010 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 04/19/2010 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/20/2010 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 04/20/2010 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 04/27/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
| 07/19/2010 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/19/2010 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/22/2010 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | |
| 07/22/2010 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/22/2010 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 08/03/2010 | PERMIT FINALED | JWEATHER | Approved |