Permit: T09CM03054
Permit Details
Apply Date:
11/19/2009
Applicant:
N/A
Description:
ADDITION:BATHROOM & FOYER & EXTEND DINING ROOM & BEDROOM
Permit Reviews
Permit Number - T09CM03054
Permit Status: Final
Permit Description: ADDITION:BATHROOM & FOYER & EXTEND DINING ROOM & BEDROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2010 | RESUBMITTAL | 02/22/2010 | COMPLETED |
| 02/22/2010 | RESUBMITTAL | 02/26/2010 | COMPLETED |
| 11/19/2009 | RESIDENTIAL BLDG/ZONING-WALKTHRU | 12/07/2009 | COMPLETED |
| 12/07/2009 | RESIDENTIAL BLDG/WWM | 01/07/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM03054
Permit Status: Final
Permit Description: ADDITION:BATHROOM & FOYER & EXTEND DINING ROOM & BEDROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/19/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM03054
Permit Description: ADDITION:BATHROOM & FOYER & EXTEND DINING ROOM & BEDROOM
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/15/2010 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 04/13/2010 | BUILDING PRE-SLAB | EDURAZO | Approved | IVRS - Inspection :* |
| 04/13/2010 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection :* |
| 04/13/2010 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection :* |
| 05/07/2010 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 05/07/2010 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 05/07/2010 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 06/12/2010 | MECHANICAL - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 06/12/2010 | PLUMBING - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 06/12/2010 | ELECTRIC - INTERMEDIATE | EDURAZO | Approved | IVRS - Inspection :* |
| 06/12/2010 | STUCCO MESH | EDURAZO | Approved | IVRS - Inspection :* |
| 06/16/2010 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 08/04/2010 | MECHANICAL - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 08/04/2010 | PLUMBING - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 08/04/2010 | ELECTRIC - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 09/28/2011 | FRAMING | DQUINN | Approved | |
| 09/28/2011 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |