Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL OTHER
Apply Date:
10/20/2009
Applicant:
N/A
Description:
TI and CofO: YOGURT SHOP
Architects:
  • BARBES, BENJAMIN
Contractors:
  • HIDDEN HOLLOW CONSTRUCTION ,

Permit Reviews

Permit Number - T09CM02811
Permit Status: C of o
Permit Description: TI and CofO: YOGURT SHOP
Start Date Submittal Complete Date Status  
10/20/2009 COMMERCIAL TI 11/06/2009 COMPLETED Review Details
11/06/2009 RESUBMITTAL 01/05/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09CM02811
Permit Status: C of o
Permit Description: TI and CofO: YOGURT SHOP
Total Outstanding Activity Conditions - 1
Date Name
10/20/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T09CM02811
Permit Description: TI and CofO: YOGURT SHOP
Total Completed Inspections - 23
Date Description Inspector Results Comments
01/22/2010 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
01/25/2010 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
02/03/2010 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) PROVIDE BEADED COLLARS ON 2 NEW SUPPLY DIFFUSERS
2) WILL CHECK ON FINAL
3) OK FOR CEILING TILES
4) TERMINATE CONDENSATE DRAINS TO AN APPROVED LOCATION
5) ALL NEW A/C UNITS WILL REQUIRE PERMITS
02/03/2010 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
1) BACKING AT MS
02/03/2010 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
02/03/2010 FRAMING JBURGE Approved IVRS - Inspection :*
02/03/2010 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
02/04/2010 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
02/10/2010 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO TAPE AND APPLY FRP
02/10/2010 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
03/08/2010 ELECTRIC - ABOVE CEILING RMORENO Approved IVRS - Inspection :*
1) CEILINGS IN BLDG ALL OK
03/30/2010 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
1) INSTALL STRAINER MISSING AT MS
03/30/2010 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
03/30/2010 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
03/30/2010 FIRE - FINAL LTHOMAS Approved Approved
03/30/2010 FIRE SPKLR - FINAL LTHOMAS Approved Approved
03/30/2010 ENGINEERING - FINAL MRUSSO Approved
03/30/2010 NPPO - FINAL JLINVILLE Approved N/A
03/30/2010 RIGHT OF WAY - FINAL M_OTERO Approved
04/07/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
04/07/2010 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
04/09/2010 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
1) ALL TRADES AND FIRE FINALS ARE COMPLETE
04/12/2010 HEALTH DEPT - FINAL 724-7908 NRAMIREZ Approved