Permit: T09CM02793
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
2518 E BLANTON DR
Address NEW:
2518 E BLANTON DR
Apply Date:
10/19/2009
Applicant:
N/A
Description:
ADDITION:BEDROOM:BATHROOM
Permit Reviews
Permit Number - T09CM02793
Permit Status: Final
Permit Description: ADDITION:BEDROOM:BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/26/2010 | REVISION - - 1ST | 02/26/2010 | COMPLETED |
| 10/19/2009 | RESIDENTIAL BLDG/ZONING-WALKTHRU | 10/19/2009 | COMPLETED |
| 10/19/2009 | RESIDENTIAL BLDG/WWM | 11/02/2009 | COMPLETED |
| 12/04/2009 | RESUBMITTAL | 12/16/2009 | COMPLETED |
| 12/16/2009 | RESUBMITTAL | 12/16/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02793
Permit Status: Final
Permit Description: ADDITION:BEDROOM:BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/19/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM02793
Permit Description: ADDITION:BEDROOM:BATHROOM
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2009 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | IVRS - Inspection :* |
| 12/22/2009 | PLUMBING - PRE SLAB | EDURAZO | Approved | IVRS - Inspection :* |
| 12/22/2009 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection :* |
| 01/20/2010 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 01/22/2010 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | IVRS - Inspection :* |
| 03/01/2010 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 04/07/2010 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/07/2010 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/07/2010 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/07/2010 | BUILDING ABOVE CEILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/08/2010 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/08/2010 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/26/2010 | SHEET ROCK NAILING | EDURAZO | Approved | IVRS - Inspection :* |
| 06/17/2010 | PLUMBING - PROGRESS | EDURAZO | Approved | IVRS - Inspection :* |
| 06/17/2010 | ELECTRIC - FINAL | EDURAZO | Approved | IVRS - Inspection :* |
| 07/27/2010 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/27/2010 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/27/2010 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 07/27/2010 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | IVRS - Inspection :* |
| 08/03/2010 | PERMIT FINALED | JWEATHER | Approved |