Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
1250 S PANTANO RD
Apply Date:
10/06/2009
Applicant:
N/A
Description:
NEW:CONVENIENCE STORE #1460
Architects:
  • FILUK, DANIEL DIMITRI
Contractors:
  • HAWORTH CORPORATION , THE

Permit Reviews

Permit Number - T09CM02693
Permit Status: C of o
Permit Description: NEW:CONVENIENCE STORE #1460
Start Date Submittal Complete Date Status  
01/26/2010 REVISION - - 1ST 01/26/2010 COMPLETED Review Details
10/06/2009 PLANS OK TO SUBMIT - COMM 10/06/2009 COMPLETED Review Details
10/06/2009 COMMERCIAL NEW 11/06/2009 COMPLETED Review Details
11/06/2009 RESUBMITTAL 01/05/2010 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09CM02693
Permit Status: C of o
Permit Description: NEW:CONVENIENCE STORE #1460
Total Outstanding Activity Conditions - 1
Date Name
10/06/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T09CM02693
Permit Description: NEW:CONVENIENCE STORE #1460
Total Completed Inspections - 45
Date Description Inspector Results Comments
12/30/2009 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
STORE BLDG FOOTING REBAR & EXCAVATION OK
SPECIAL INSPECTION BY KEILFELDER
12/30/2009 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
01/04/2010 STEM WALL/RETAINING WALL GDABBS Approved IVRS - Inspection :*
1) CMU STEM WALLS AT STORE STRUCTURE (2 COURSES) OK TO GROUT
2) PAID AFTER HOURS INSPECTION AND RECEIVED $150.00 CHECK #02778
01/11/2010 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
01/14/2010 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
01/14/2010 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
02/04/2010 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
02/08/2010 ROOF NAILING GDABBS Approved IVRS - Inspection :*
1) ROOF DECK PUDDLE WELDS AND BUTTON PUNCH JOISTS AND X-BRACING OK
2) SPECIAL INSPECTION BY KLEINFELDER
02/16/2010 FRAMING GDABBS Approved IVRS - Inspection :*
02/18/2010 PLUMBING - ROOF DRAINS RRICH Approved IVRS - Inspection :*
02/18/2010 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
02/18/2010 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
02/18/2010 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
02/26/2010 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
1) SHEETROCK & PLYWOOD SHEATHING FOR SHELVING; RESTROOMS OK TO TAPE THROUGHOUT
03/26/2010 ELECTRIC - TEMPORARY SERVICE RJIROUDE Approved IVRS - Inspection :*
1) ELECTRICAL CONTRACTOR TO USE LOCK OUT PROCEDURES TO ENSURE CONTROL OF DISTRIBUTION SYSTEM
03/29/2010 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER R. JIROUDEK
03/30/2010 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
1) INDIRECT DRAIN AT COFFEE BAR OK
03/30/2010 PLUMBING - PROGRESS RRICH Approved IVRS - Inspection :*
03/31/2010 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1) INSULATE LINEAR BOXES WITH MINIMUM R4.2 WILL CHECK ON FINAL
03/31/2010 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
03/31/2010 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
04/14/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) AIR BALANCE AND DUCT SMOKE DETECTOR TEST OK
2) OK FOR FINAL
04/15/2010 NPPO - FINAL DROBERTS Approved
04/15/2010 LANDSCAPE - FINAL DROBERTS Approved
04/15/2010 ENGINEERING - FINAL DROBERTS Approved THE SITE WAS CHECKED FOR THE ENGINEERING ASPECTS AND HAS BEEN APPROVED AT THIS TIME. AN AS-BUILT OF THE GRADING PLANS HAS BEEN PROVIDED ALONG WITH A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD.
04/15/2010 FIRE SPKLR - FINAL CSCHULTZ Approved
04/15/2010 FIRE - FINAL CSCHULTZ Approved
04/15/2010 REINFORCED MASONRY PRE-GROUT GDABBS Approved IVRS - Inspection :*
04/15/2010 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
04/15/2010 BUILDING - PROGRESS GDABBS Approved IVRS - Inspection :*
04/15/2010 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
04/15/2010 OUTDOOR LIGHTING FINAL RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - OUTDOOR LIGHTING RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - TEMP POWER FOR TEST RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - PROGRESS RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - CABLE DROP RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
04/15/2010 ELECTRIC - UNDERGROUND RJIROUDE Approved IVRS - Inspection :*
04/16/2010 BUILDING - FINAL MHENSON Approved IVRS - Inspection :*
1) HAD COMPLIANT SPECIAL INSPECTIONS ON SITE
04/19/2010 SIGN - FINAL JYBARRA Approved
04/20/2010 RIGHT OF WAY - FINAL MCASTRO Approved
04/20/2010 HEALTH DEPT - FINAL 724-7908 NRAMIREZ Approved
04/20/2010 STUCCO MESH MHENSON Approved