Permit: T09CM02693
Permit Details
Apply Date:
10/06/2009
Applicant:
N/A
Description:
NEW:CONVENIENCE STORE #1460
Architects:
- FILUK, DANIEL DIMITRI
Contractors:
- HAWORTH CORPORATION , THE
Permit Reviews
Permit Number - T09CM02693
Permit Status: C of o
Permit Description: NEW:CONVENIENCE STORE #1460
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/26/2010 | REVISION - - 1ST | 01/26/2010 | COMPLETED |
10/06/2009 | PLANS OK TO SUBMIT - COMM | 10/06/2009 | COMPLETED |
10/06/2009 | COMMERCIAL NEW | 11/06/2009 | COMPLETED |
11/06/2009 | RESUBMITTAL | 01/05/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02693
Permit Status: C of o
Permit Description: NEW:CONVENIENCE STORE #1460
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/06/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02693
Permit Description: NEW:CONVENIENCE STORE #1460
Total Completed Inspections - 45
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/30/2009 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* STORE BLDG FOOTING REBAR & EXCAVATION OK SPECIAL INSPECTION BY KEILFELDER |
12/30/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* |
01/04/2010 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* 1) CMU STEM WALLS AT STORE STRUCTURE (2 COURSES) OK TO GROUT 2) PAID AFTER HOURS INSPECTION AND RECEIVED $150.00 CHECK #02778 |
01/11/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
01/14/2010 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
01/14/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
02/04/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
02/08/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* 1) ROOF DECK PUDDLE WELDS AND BUTTON PUNCH JOISTS AND X-BRACING OK 2) SPECIAL INSPECTION BY KLEINFELDER |
02/16/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
02/18/2010 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
02/18/2010 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
02/18/2010 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
02/18/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
02/26/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) SHEETROCK & PLYWOOD SHEATHING FOR SHELVING; RESTROOMS OK TO TAPE THROUGHOUT |
03/26/2010 | ELECTRIC - TEMPORARY SERVICE | RJIROUDE | Approved | IVRS - Inspection :* 1) ELECTRICAL CONTRACTOR TO USE LOCK OUT PROCEDURES TO ENSURE CONTROL OF DISTRIBUTION SYSTEM |
03/29/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
03/30/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* 1) INDIRECT DRAIN AT COFFEE BAR OK |
03/30/2010 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
03/31/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) INSULATE LINEAR BOXES WITH MINIMUM R4.2 WILL CHECK ON FINAL |
03/31/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
03/31/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
04/14/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) AIR BALANCE AND DUCT SMOKE DETECTOR TEST OK 2) OK FOR FINAL |
04/15/2010 | NPPO - FINAL | DROBERTS | Approved | |
04/15/2010 | LANDSCAPE - FINAL | DROBERTS | Approved | |
04/15/2010 | ENGINEERING - FINAL | DROBERTS | Approved | THE SITE WAS CHECKED FOR THE ENGINEERING ASPECTS AND HAS BEEN APPROVED AT THIS TIME. AN AS-BUILT OF THE GRADING PLANS HAS BEEN PROVIDED ALONG WITH A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD. |
04/15/2010 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
04/15/2010 | FIRE - FINAL | CSCHULTZ | Approved | |
04/15/2010 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
04/15/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
04/15/2010 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
04/15/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
04/15/2010 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
04/16/2010 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) HAD COMPLIANT SPECIAL INSPECTIONS ON SITE |
04/19/2010 | SIGN - FINAL | JYBARRA | Approved | |
04/20/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
04/20/2010 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
04/20/2010 | STUCCO MESH | MHENSON | Approved |