Permit: T09CM02485
Permit Details
Apply Date:
09/15/2009
Applicant:
N/A
Description:
NEW SFR MIRA 23331
Contractors:
- MIRAMONTE ARIZONA L L C *C
Permit Reviews
Permit Number - T09CM02485
Permit Status: Final
Permit Description: NEW SFR MIRA 23331
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/15/2009 | RESIDENTIAL BLDG-MODEL PLAN/ENGINE/WALK THRU | 09/15/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02485
Permit Status: Final
Permit Description: NEW SFR MIRA 23331
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/15/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM02485
Permit Description: NEW SFR MIRA 23331
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2009 | PLUMBING - ROUGH, SOIL | EDURAZO | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) 2 WAY CLEANOUT REQUIRED AT BACK WATER VALVE |
| 10/02/2009 | PLUMBING - YARD WTR LINE/TEST | EDURAZO | Approved | IVRS - Inspection :* |
| 10/05/2009 | PLUMBING - SEWER HCS CONNECT | EDURAZO | Approved | IVRS - Inspection :* |
| 10/13/2009 | BUILDING PRE-SLAB | EDURAZO | Approved | |
| 10/13/2009 | ELECTRIC - UFER | EDURAZO | Approved | IVRS - Inspection :* 1) REBAR STUB FOR FUTURE GROUND |
| 10/13/2009 | EXCAVATION/LAYOUT REBAR & ZON | EDURAZO | Approved | IVRS - Inspection :* |
| 11/04/2009 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* 1) ALL FIREWALL CLIPS OK TO COVER |
| 11/04/2009 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2009 | ELECTRIC - TEMPORARY SERVICE | DQUINN | Approved | |
| 11/16/2009 | ELECTRIC - CABLE DROP | DQUINN | Approved | IVRS - Inspection :* |
| 11/17/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER D. QUINN |
| 11/20/2009 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 11/20/2009 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 11/20/2009 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 11/20/2009 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 11/24/2009 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 11/24/2009 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 12/30/2009 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 02/24/2010 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 02/25/2010 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 02/25/2010 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 02/25/2010 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 02/26/2010 | PERMIT FINALED | JWEATHER | Approved |