Permit: T09CM02007
Permit Details
Apply Date:
07/28/2009
Applicant:
N/A
Description:
TI: CEEDEE JAMAICAN KITCHEN
Architects:
- MAHER, JOSEPH SAID JR
Contractors:
- PHILIP'S PLUMBING , *C
Permit Reviews
Permit Number - T09CM02007
Permit Status: C of o
Permit Description: TI: CEEDEE JAMAICAN KITCHEN
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/03/2010 | REVISION - - 1ST | 02/03/2010 | COMPLETED |
| 07/28/2009 | PLANS OK TO SUBMIT - COMM | 07/28/2009 | COMPLETED |
| 07/28/2009 | COMMERCIAL TI | 09/14/2009 | COMPLETED |
| 10/26/2009 | RESUBMITTAL | 02/03/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02007
Permit Status: C of o
Permit Description: TI: CEEDEE JAMAICAN KITCHEN
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/28/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02007
Permit Description: TI: CEEDEE JAMAICAN KITCHEN
Total Completed Inspections - 16
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 02/12/2010 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 03/03/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | |
| 03/03/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | |
| 03/03/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) FAN AND LIGTHS IN HOOD WORK, J-BOX GROUNDING, SUB-PANEL, EXHAUST FAN AND DISCONNECT SWITCH ALL OK |
| 03/17/2010 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* 1) GAS TEST OK CLEARANCE PROVIDED, PROVIDE CORRECTLY SIZED CONNECTIONS TO GAS EQUIPMENT NOTE: RP INSTALL REQUIRES CLEARNACE TO VALVE HANDLES AND A TUCSON WATER PERMIT |
| 03/18/2010 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 03/19/2010 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 03/22/2010 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 03/31/2010 | FIRE - KITCHEN EXH HOOD FINAL | DRAMIREZ | Approved | Approved |
| 04/05/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/08/2010 | FIRE - FINAL | DRamirez | Approved | Approved 4/7/10 |
| 04/09/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/12/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) FIRE AND TRADES ARE COMPLETE |
| 04/23/2010 | HEALTH DEPT - FINAL 724-7908 | ELOPEZ | Approved | PER LETTER |