Permit: T09CM01671
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
8198 S CAMINO DE CAFE
Address NEW:
8198 S CAMINO DE CAFE
Apply Date:
06/29/2009
Applicant:
N/A
Description:
TI:FACTORY
Architects:
- ARMSTRONG, TERRY
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T09CM01671
Permit Status: C of o
Permit Description: TI:FACTORY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/29/2009 | PLANS OK TO SUBMIT - 3RD PARTY | 06/30/2009 | COMPLETED |
| 06/30/2009 | 3RD PARTY REVIEW-COMMERCIAL | 07/16/2009 | COMPLETED |
| 07/08/2010 | REVISION - - 1ST | 07/14/2010 | COMPLETED |
| 07/16/2009 | POST 3RD PARTY REVIEW | 07/30/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01671
Permit Status: C of o
Permit Description: TI:FACTORY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/29/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01671
Permit Description: TI:FACTORY
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* 1) NEED HOLDOWNS (2) INSTALLED AT INTERIOR SEPERATION WALL |
| 07/14/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 11/04/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) DWV AND WATER OK 2) CLOSET FLANGES OK FOR CONNECTOR VCT. |
| 12/01/2010 | ENGINEERING - FINAL | DROBERTS | Approved | SITE NOT READY AT THIS TIME, CHANGES HAVE BEEN MADE TO THE SITE THAT ARE NOT REFLECTIVE ON THE APPROVED SITE AND GRADING PLANS. APPROVED REVISIONS OF THE SITE WILL NEED TO BE PROVIDED FOR THIS FINAL INSPECTION. |
| 12/01/2010 | NPPO - FINAL | DROBERTS | Approved | I WILL CONTACT ANDREW CONNOR OR JOSEPH LINVILLE IN REGARDS TO THIS INSPECTION ONCE IT HAS BEEN REQUESTED. |
| 12/01/2010 | LANDSCAPE - FINAL | DROBERTS | Approved | MINOR ITEMS WITH THE PLANTS VIABILITY WILL BE CHECKED DURING THE FINAL ENGINEERING INSPECTION. DUE TO FREEZING TEMPERATURES THIS WEEK SOME OF THE PLANTS MAY HAVE BEEN DAMAGED AND WILL NEED TO BE REPLACED. THE DEVELOPER HAS ALREADY REPLACED SOME OF THE PLANTS AND IS AWARE HE MAY HAVE TO REPLACE EVEN MORE BEFORE ALL FINALS ARE ACCEPTED. |
| 12/01/2010 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/01/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/22/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 12/22/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 12/28/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
| 12/28/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/28/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 12/28/2010 | SIGN - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 12/28/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/28/2010 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/28/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/28/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 02/15/2011 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 02/15/2011 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 02/17/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 02/17/2011 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |