Permit: T09CM01660
Permit Details
Apply Date:
06/29/2009
Applicant:
N/A
Description:
NEW DOCTORS OFFICE
Architects:
- PODOLSKY, WILLIAM I
Contractors:
- TUCSON PATIO WALLS INC *C
- BORDERLAND CONSTRUCTION COMPANY *C
Permit Reviews
Permit Number - T09CM01660
Permit Status: C of o
Permit Description: NEW DOCTORS OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/29/2009 | PLANS OK TO SUBMIT - COMM | 06/29/2009 | COMPLETED |
| 06/29/2009 | COMMERCIAL NEW | 07/17/2009 | COMPLETED |
| 07/17/2009 | RESUBMITTAL | 07/17/2009 | COMPLETED |
| 07/17/2009 | RESUBMITTAL | 07/29/2009 | COMPLETED |
| 09/29/2009 | REVISION - - 1ST | 10/07/2009 | COMPLETED |
| 10/21/2009 | REVISION - - 2ND | 10/22/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01660
Permit Status: C of o
Permit Description: NEW DOCTORS OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/29/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01660
Permit Description: NEW DOCTORS OFFICE
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/10/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* 1) UFER OK |
| 08/14/2009 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* 1) CONTINOUS STEM WALL AT 0'-16" OK TO POUR |
| 08/21/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 08/28/2009 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* 1) BLDG PRE-SLAB AND 9 FH/C3 COLUMN STEMS FOR PORCH-OK |
| 08/28/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 10/13/2009 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 10/23/2009 | ELECTRIC - TEMPORARY SERVICE | RMORENO | Approved | IVRS - Inspection :* 1) SERVICE WIRES, GROUNDING AND TEMP POLE OK |
| 10/27/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) WEST PORCH AND CANOPY AREAS ARE COMPLETE-OK TO DRY IN AND COVER 2) RECEIVED ENGINEERING REPORT FOR TRUSS ALTERATION AT ROOF ACCESS-DATED 10/15/09 |
| 10/27/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. MORENO-SENT TO TEP ON 10/26/09 IN THE AM PER R. MAJUTA |
| 11/17/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 4 LIGHT POLE CAISSON FOOTINGS AS PER DETAILS-OK TO POUR FOOTINGS |
| 11/17/2009 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | 2 TRASH ENCLOSURES TOPPED OUT (R-1) OK TO GROUT PROGRESS AREAS |
| 11/17/2009 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) POLE LIGHTING ON NORTH OF BLDG, POLE LIGHTING SOUTH OF BLDG OK |
| 11/17/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 11/19/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK OT SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
| 11/23/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* 1) DWV WITH TEST OK 2) DOMESTIC WATER WITH 55 PSI TEST 3) REMOVE EXCESS FLUX PRIOR TO INSULATION 4) RECALL FOR INSPECTION AFTER INSTALLING INSULATION PER MANUFACTURES SPECS 5) RECALL FOR CLOSET FLANGES AFTER FINISHED FLOOR |
| 11/23/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 11/24/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO |
| 11/24/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) WALLS IN BLDG OK |
| 12/02/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* FRONT SOFIT LITES, 5 BATHROOMS, 2 CLOSETS, HARD LIDS ALL OK |
| 12/07/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) OK TO ROCK LIDS |
| 12/07/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 12/07/2009 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 12/08/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
| 01/21/2010 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
| 02/01/2010 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 02/08/2010 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* 1) SERVICE WIRES, GROUNDING AND BONDING ALL OK |
| 02/11/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 02/16/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 02/18/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) CARPORT AND PARKING LOT LIGHTS OK 2) BLDG ELECTRICAL FINAL OK |
| 02/18/2010 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 02/19/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 02/19/2010 | RIGHT OF WAY - FINAL | PWhiddon | Approved | |
| 02/22/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 02/22/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 02/23/2010 | MECHANICAL - FINAL | JMILLITEL | Approved | 1) AIR BALANCE REPORT OK 2) NEED TO DO DUCT SMOKE DETECTOR TEST ON RTU-S 3) OK FOR FINAL 4) TESTED DUCT SMOKE DETECTOR |
| 02/23/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE |
| 02/23/2010 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 02/23/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 02/23/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 02/23/2010 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 02/23/2010 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
| 02/26/2010 | NPPO - FINAL | JLINVILLE | Approved | PER INSP CARD |
| 02/26/2010 | LANDSCAPE - FINAL | JLINVILLE | Approved | PER INSP CARD |
| 02/26/2010 | ENGINEERING - FINAL | MRUSSO | Approved |