Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2009 | REINFORCED MASONRY PRE-GROUT | Approved | 2 TRASH ENCLOSURES TOPPED OUT (R-1) OK TO GROUT PROGRESS AREAS | |
| 09/21/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 1) ALL WALLS TOPPED OUT AT 18'-18' 8" 2) OK TO GROUT PROGRESS AREAS |
|
| 09/18/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) NORTH AND SOUTH WALLS AT 16'-WEST WALL 14'-4" (LEDGER BOLTS AND BEAM SADDLES ARE IN PLACE, OK TO GROUT PROGRESS AREAS |
|
| 09/17/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* EAST WALL & SE CORNER - TOPPED OUT AT 15' OK TO GROUT PROGRESS AREA |
|
| 09/14/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) PARTIAL 3RD LIFT AT 8'-4"-12'; OK TO GROUT PROGRESS AREAS |
|
| 09/09/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 2ND LIFT @4'-8' AFFE - OK TO GROUT PROGRESS AREAS |
|
| 09/04/2009 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT AT 0"-48" AFFE-OK TO GROUT PROGRESS AREA |