Permit: T09CM01599
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
7333 E TANQUE VERDE RD
Address NEW:
7333 E TANQUE VERDE RD
Apply Date:
06/23/2009
Applicant:
N/A
Description:
NEW MEDICAL OFFICE BLDG C OF O ISSUED 12/08/09
Architects:
- EGLIN, EVAN SAR
Contractors:
- VENTURE WEST INC *C
Permit Reviews
Permit Number - T09CM01599
Permit Status: C of o
Permit Description: NEW MEDICAL OFFICE BLDG
C OF O ISSUED 12/08/09
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2009 | PLANS OK TO SUBMIT - COMM | 06/23/2009 | COMPLETED |
| 06/23/2009 | 3RD PARTY REVIEW-COMMERCIAL | 07/27/2009 | COMPLETED |
| 07/27/2009 | POST 3RD PARTY REVIEW | 08/24/2009 | COMPLETED |
| 10/06/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 10/06/2009 | COMPLETED |
| 12/02/2009 | REVISION - - 1ST | 12/02/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM01599
Permit Status: C of o
Permit Description: NEW MEDICAL OFFICE BLDG
C OF O ISSUED 12/08/09
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/23/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM01599
Permit Description: NEW MEDICAL OFFICE BLDG
C OF O ISSUED 12/08/09
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/19/2009 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 08/20/2009 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 08/27/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* 1) SLAB AREA COMPACTED |
| 08/27/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) CONTINOUS FOOTINGS/COLUMNS-OK TO POUR |
| 08/27/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* 1) UFER 3/0 OK |
| 08/27/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
| 09/21/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) EXTERIOR AND INTERIOR METAL & WOOD FRAMING 2) OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
| 10/06/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO DRY IN |
| 10/06/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO COVER EXTERIOR WALLS |
| 10/06/2009 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/08/2009 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
| 10/14/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 10/15/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) WALLS IN BLDG OK |
| 10/19/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE AND TEXTURE THROUGHOUT |
| 10/19/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO EXTERIOR WALLS |
| 10/19/2009 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 10/19/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 11/05/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* 1) NEED LOW VOLTAGE BUSHINGS |
| 11/05/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 11/06/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 11/12/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 11/17/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/19/2009 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* 1) NEED TO CLEAN BOTTOM OF PANEL 2) SERVICE WIRES, GROUNDING AND BONDING OK |
| 11/20/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. MORENO |
| 11/27/2009 | FIRE - FINAL | LThomas | Approved | Approved 11/27/09. |
| 11/30/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 11/30/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 11/30/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 11/30/2009 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 11/30/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 11/30/2009 | NPPO - FINAL | JLINVILLE | Approved | N/A |
| 11/30/2009 | LANDSCAPE - FINAL | JLINVILLE | Approved | N/A |
| 11/30/2009 | NPPO - FINAL | JLINVILLE | Approved | |
| 12/01/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 12/02/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* BATHROOM EXHAUSE IS TO BE ON A TIME CLOCK SET TO RUN DURING OCCUPIED HOURS AS PER PLANS. FANS ON A/C UNITS TO BE LOCKED IN THE "ON" POSITION AIR BALANCE IS OK BLDG INSPECTOR WILL CONFIRM CORRECTIONS. OK FOR FINAL |
| 12/03/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/03/2009 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 12/07/2009 | ENGINEERING - FINAL | JFEMLING | Approved | Approved |
| 12/08/2009 | PERMIT FINALED | JWEATHER | Approved |