Permit: T09CM00365
Permit Details
Apply Date:
02/17/2009
Applicant:
N/A
Description:
NEW: MEDICAL BUILDING
Contractors:
- VENTURE WEST INC *C
Permit Reviews
Permit Number - T09CM00365
Permit Status: C of o
Permit Description: NEW: MEDICAL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/17/2009 | PLANS OK TO SUBMIT - 3RD PARTY | 02/18/2009 | COMPLETED |
02/18/2009 | 3RD PARTY REVIEW-COMMERCIAL | 03/26/2009 | COMPLETED |
03/26/2009 | POST 3RD PARTY REVIEW | 03/31/2009 | COMPLETED |
05/19/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 05/19/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00365
Permit Status: C of o
Permit Description: NEW: MEDICAL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/17/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00365
Permit Description: NEW: MEDICAL BUILDING
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/16/2009 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
04/20/2009 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
05/05/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* SERVICE AND PHONE UFER OK |
05/05/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR SLAB |
05/05/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CONTINUOUS FOOTINGS -- OK TO POUR FOOTINGS |
05/06/2009 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
06/03/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) ROOF SYSTEM NAILED-PARAPET WALLS COVERED AND NAILED 2) OK TO DRY IN ROOF SYSTEM |
06/03/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* 1) METAL CLIPS IN PLACE; EXTERIOR SHEATHING NAILED PER PLANS |
06/23/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* SOFFITS & RECEPTION AREA COMPLETE - OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES |
07/07/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) N,S,E SIDES HAVE BEEN SCRATCH COATED-UNABLE TO INSPECT THESE AREAS |
07/08/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK MECHANICAL |
07/09/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) NEED PLASTIC BUSHINGS ON LOW VOLTAGE PIPE OR FLEX FOR FINAL 2) SOFFIT CAN LIGHTS-OK |
07/10/2009 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
07/10/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/14/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
08/10/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* 1) PLAN HAS CONFLICT IN SIZING 1) 1" SOFT CU INSTALLED, PLUMBING PER KEN CAUTHERN SYSTEM WILL WORK WITH 1" |
08/11/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
08/20/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES FOR FINAL PROVIDE THE OBD DAMPERS IN SUPPLY DIFFUSERS OR PROVIDE A LETTER FROM THE ENGINEER TO DELETE |
08/20/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* CEILINGS IN BUILDINGS OK |
08/27/2009 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* 1) TEMPERED GLASS SYSTEM AT ALL DOORS |
08/27/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) T-GRID SYSTEM CEILING TILES IN PLACE |
08/27/2009 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* 1) SECONDARYS OK |
08/28/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. MORENO |
08/31/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
08/31/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
09/01/2009 | NPPO - FINAL | ACONNOR | Approved | |
09/10/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
09/11/2009 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
09/22/2009 | FIRE - FINAL | LTHOMAS | Approved | |
09/22/2009 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
09/22/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
09/23/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) PERMANENT ACCESS TO ROOF WILL BE PROVIDED WHEN THE NEW BLDG IS ADDED TO THE SITE 2) OK FOR FINAL |
09/23/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* 1) EXITS, LABELS AND EM LIGHTS ALL OK |
09/23/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
09/24/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
09/25/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) ALL TRADES AND FIRE FINALS ARE COMPLETE |
09/28/2009 | PERMIT FINALED | JWEATHER | Approved |