Permit: T09CM00284
Permit Details
Apply Date:
02/05/2009
Applicant:
N/A
Description:
REMODEL: TOILET FOR ACCESSIBILITY COMPLIANCE
Contractors:
- WARRIOR CONSTRUCTION L L C
Permit Reviews
Permit Number - T09CM00284
Permit Status: Final
Permit Description: REMODEL: TOILET FOR ACCESSIBILITY COMPLIANCE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2009 | COMMERCIAL TI | 02/10/2009 | COMPLETED |
| 02/10/2009 | RESUBMITTAL | 02/12/2009 | COMPLETED |
| 02/27/2009 | REVISION - - 1ST | 02/27/2009 | COMPLETED |
| 02/27/2009 | REVISION - - 2ND | 02/27/2009 | COMPLETED |
| 03/26/2009 | REVISION - - 3RD | 03/26/2009 | COMPLETED |
| 03/26/2009 | REVISION - - 3RD | 03/26/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00284
Permit Status: Final
Permit Description: REMODEL: TOILET FOR ACCESSIBILITY COMPLIANCE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/05/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM00284
Permit Description: REMODEL: TOILET FOR ACCESSIBILITY COMPLIANCE
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/31/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1. OK FOR CONCRETE PVC WATER TEST THRU THE ROOF OK 2. SPEED FIT "SHARK BITE" CAPS UPC APPROVED |
| 03/31/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 04/07/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* WALLS OK |
| 04/07/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK PENDING PLUMBING INTERMEDIATE |
| 04/10/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :$ OK TO TAPE THROUGHOUT |
| 04/15/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
| 04/16/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 04/17/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | |
| 04/17/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 04/17/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/17/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 04/20/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 04/21/2009 | FIRE - FINAL | DRAMIREZ | Approved | |
| 04/21/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 04/21/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 04/21/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 04/21/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 04/21/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 04/21/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 04/21/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |