Permit: T09BU01625
Permit Details
Apply Date:
10/30/2009
Applicant:
GLHM ARCHITECTECTS & ENG
Description:
GRADING:SUN TRAN PHASE 3
Contractors:
- WITHERS CONSTRUCTION L C , D L
Permit Reviews
Permit Number - T09BU01625
Permit Status: Final
Permit Description: GRADING:SUN TRAN PHASE 3
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/31/2010 | RESUBMITTAL - GRADING | 10/19/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09BU01625
Permit Status: Final
Permit Description: GRADING:SUN TRAN PHASE 3
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/30/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09BU01625
Permit Description: GRADING:SUN TRAN PHASE 3
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/08/2010 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | MET WITH SUPERINTENDENT AND DISCUSSED SWPPP. SEDIMENT CONTROLS AND STABILIZE CONSTRUCTION ENTRANCES HAVE BEEN INSTALLED. ENSURE CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION. ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. CALL FOR RE-INSPECTION. |
10/22/2010 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | RAINING TODAY: PERIMETER STORM WATER CONTROLS HAVE BEEN INSTALLED. SWEEP TRACKED SOIL OFF ROADWAYS. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. SOME WORK BEING DONE ON BLDG ALONG WEST SIDE OF SITE. STORM DRAINAGE IN SOUTH PARKING LOT DONE DURING PHASE II DOES NOT DRAIN PROPERLY |
12/15/2010 | GRADING - INTERMEDIATE | MRUSSO | Approved | |
12/15/2010 | STORMWATER FOLLOW-UP INSP | MRUSSO | Approved | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. NO SITE WORK AT THIS TIME. |
01/04/2012 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | CONSTRUCTION HAS BEEN COMPLETED, PHASE III OF THE MAINT FACILITY. ALL SITE WORK HAS BEEN CONSTRUCTED PER THE APPROVED PLANS. SITE IS 100% STABILIZED. |
01/05/2012 | GRADING - CHECK FOR ACTIVITY | MRUSSO | Approved | |
01/05/2012 | GRADING - REBAR | MRUSSO | Approved | |
01/05/2012 | GRADING - FINAL | MRUSSO | Approved | CONSTRUCTION HAS BEEN COMPLETED, PHASE III OF THE MAINT FACILITY. ALL SITE WORK HAS BEEN CONSTRUCTED PER THE APPROVED PLANS. SITE IS 100% STABILIZED. A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD IS ON FILE FROM PREVIOUS PHASES OF THIS PROJECT. |
03/01/2012 | PERMIT FINALED | KMEDINA | Approved |