Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Grading and SWPPP
Apply Date:
04/14/2009
Applicant:
WARREN D THOMPSON
Description:
GRADING:
Contractors:
  • BORDERLAND CONSTRUCTION COMPANY *C

Permit Reviews

Permit Number - T09BU00539
Permit Status: Final
Permit Description: GRADING:
Start Date Submittal Complete Date Status  
04/14/2009 GRADING 06/04/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09BU00539
Permit Status: Final
Permit Description: GRADING:
Total Outstanding Activity Conditions - 1
Date Name
04/14/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T09BU00539
Permit Description: GRADING:
Total Completed Inspections - 12
Date Description Inspector Results Comments
06/15/2009 NPPO PRE PERMIT INSPECTION ACONNOR Approved
06/26/2009 ENGINEERING PRE-CONSTRUCTION DROBERTS Approved MET WITH MIKE BOWERS FROM BORDERLAND AND LOOKED OVER THE PAPER WORK FOR THIS PROJECT. HE SIGNED THE PAPERS AND I WILL PROVIDE HIM A COPY OF THE DOCUMENT ON 6/29/09. THE STORM WATER CONTROLS (GRADER DITCH) HAVE BEEN INSTALLED ON THIS PROJECT, AND THE SITE HAS BEEN DE-VEGITATED AND MULCHED. I WILL CHECK THIS SITE MONTHLY UNTIL THE EXCAVATING HAS BEEN COMPLETED AND THE SITE HAS BEEN PUT TO REST. THE WORK ON THIS PORTION OF THE PROJECT CONSIST OF JUST THE HAUL OFF AND PLACEMENT OF MATERIAL AT THE INTERSECTION OF OLD VAIL ROAD AND HOUGHTON.
10/10/2010 GRADING - CHECK FOR ACTIVITY DROBERTS Approved NO WORK AT THIS TIME.
05/16/2011 LANDSCAPE INSPECTION DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 STORMWATER FINAL INSPECTION DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 STORMWATER FOLLOW-UP INSP DROBERTS Approved
05/16/2011 STORMWATER INSTALL OF CONTROLS DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 GRADING - FINAL DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 GRADING - INTERMEDIATE DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 GRADING - REBAR DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/16/2011 GRADING - TIER REV DROBERTS Approved SITE WORK COMPLETE FOR ROUGH GRADING.
05/24/2011 PERMIT FINALED KMEDINA Approved

Documents

File Name Document Type  
001_1 OF 7.TIF GRADING PLANS VIEW
002_2 OF 7.TIF GRADING PLANS VIEW
003_5 OF 7.TIF GRADING PLANS VIEW
004_6 OF 7.TIF GRADING PLANS VIEW
None DOCUMENTS VIEW
BOND RELEASE LETTER 2011_05_26.PDF DOCUMENTS VIEW