Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/16/2011 |
GRADING - FINAL |
|
Approved |
SITE WORK COMPLETE FOR ROUGH GRADING. |
| 03/03/2010 |
GRADING - FINAL |
|
Continued |
MET WITH MIKE BOWERS AND LOOKED AT THE SITE IN THE CURRENT CONDITION. HE HAS FINISHED THE REMOVAL OF THE CURRENT STOCKPILE THAT HAS BEEN ON-SITE SINCE THE START OF THE PROJECT. HE WILL BE BRINGING BACK ADDITIONAL MACHINERY IN THE NEXT WEEK OR TWO TO RE-START THE REMOVAL OF THE EXCESS MATERIAL. HE WILL CONTINUE TO MONITOR THE STORM WATER CONTROLS FOR THIS SITE AS HE HAS BEEN DOING IN THE PAST. |