Permit: T08CM03978
Permit Details
Apply Date:
12/24/2008
Applicant:
N/A
Description:
TI:PAYLESS SHOE SOURCE
Contractors:
- TRI RIVER DESIGN AND CONSTRUCTION INC
Permit Reviews
Permit Number - T08CM03978
Permit Status: C of o
Permit Description: TI:PAYLESS SHOE SOURCE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/21/2009 | POST 3RD PARTY REVIEW | 02/13/2009 | COMPLETED |
12/24/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 12/24/2008 | COMPLETED |
12/24/2008 | 3RD PARTY REVIEW-COMMERCIAL | 01/21/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03978
Permit Status: C of o
Permit Description: TI:PAYLESS SHOE SOURCE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/24/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03978
Permit Description: TI:PAYLESS SHOE SOURCE
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/30/2009 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
04/02/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES PROVIDE FIRE DAMPERS IN DEMISING WALL WILL CHECK ON FINAL ALSO, PROVIDE AIR BALANCE REPORT FOR FINAL |
04/02/2009 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
04/06/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* FIRE DAMPERS OK OK FOR FINAL |
04/07/2009 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
04/08/2009 | NPPO - FINAL | ACONNOR | Approved | |
04/08/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/08/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
04/08/2009 | FIRE - FINAL | LTHOMAS | Approved | |
04/09/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
04/09/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
04/10/2009 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
04/10/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
04/14/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
04/14/2009 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
04/14/2009 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
04/15/2009 | PERMIT FINALED | LJACKSON | Approved | |
04/15/2009 | BUILDING - FINAL | AQUIROZ | Approved | |
04/15/2009 | BUILDING ABOVE CEILING | JYBARRA | Approved | |
04/15/2009 | SIGN - FINAL | JYBARRA | Approved | |
04/15/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |