Permit Number - T08CM03375
Permit Status: C of o
Permit Description: TI:RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 01/21/2009 | COMPLETED |
10/15/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 10/15/2008 | COMPLETED |
10/15/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/28/2008 | COMPLETED |
11/28/2008 | POST 3RD PARTY REVIEW | 12/17/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03375
Permit Status: C of o
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/15/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03375
Permit Description: TI:RETAIL
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/11/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
01/08/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
01/09/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
01/13/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK THROUGHOUT |
01/16/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
02/03/2009 | TEP CLEARANCE - PM | BFLORES | Approved | TEC STE.#151 PER R.MORENO |
02/11/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* AIR BALANCE OK |
02/11/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
02/11/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
02/11/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
02/11/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* COMPLETE THE WORK FROM 1/8 |
02/11/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
02/11/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OPEN CEILING SYSTEM |
02/11/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
02/11/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
02/11/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
02/11/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
02/11/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
02/11/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
02/11/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
02/11/2009 | ELECTRIC - PROGRESS | RMORENO | Approved | IVRS - Inspection :* |
02/11/2009 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
02/11/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
02/11/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
02/11/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
02/11/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/11/2009 | FIRE - FINAL | LTHOMAS | Approved | |
02/12/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* 1) TRADES AND FIRE FINALS COMPLETE |
02/18/2009 | PERMIT FINALED | LJACKSON | Approved | |
02/18/2009 | SIGN - FINAL | JYBARRA | Approved | FOR ISSUING C OF O |
02/18/2009 | SIGN - FINAL | JYBARRA | Approved | BOND POSTED UNDER T08OT02844 |