Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM03217
Permit Details
Apply Date:
09/29/2008
Applicant:
N/A
Description:
NEW MEDICAL BUILDING
Contractors:
- VENTURE WEST CONSTRUCTION L L C
- VENTURE WEST INC *C
Permit Reviews
Permit Number - T08CM03217
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/11/2009 | REVISION - - 1ST | 02/18/2009 | COMPLETED |
09/29/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 09/30/2008 | COMPLETED |
09/30/2008 | 3RD PARTY REVIEW-COMMERCIAL | 11/17/2008 | COMPLETED |
11/17/2008 | POST 3RD PARTY REVIEW | 11/26/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03217
Permit Status: C of o
Permit Description: NEW MEDICAL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/29/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03217
Permit Description: NEW MEDICAL BUILDING
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2008 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
12/24/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* 1. INSTALLED PER PLAN 2. OK TO COVER 3. REVISE COVER PAGE CODE ANALYSIS AND P-1 OR PROVIDE PETITION OF APPEAL TO USE IPC |
12/30/2008 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) NORTH WEST CORNER PANEL FEEDER 2 1/2 AND 1 1/2 FROM NORTH EAST CORNER FROM SERVICE 2) PHONE, DATA MIDWAY |
01/08/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* OK 1 # 1/0 CU BOND |
01/08/2009 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR SLAB |
01/08/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CONTINUOUS FOOTINGS (F-1) SHEAR WALL FOOTINGS (F-4, F-5) COLUMN FOOTINGS C1/F3, C2/F4 - OK TO POUR PROGRESS AREAS |
01/30/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* CRICKETS & SCUPPERS ARE COMPLETE OK TO COVER ROOF SYSTEM |
01/30/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO MESH EXTERIOR |
02/24/2009 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
03/02/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* CAULK AROUND NORTH HOSE BIB - OK TO STUCCO THROUGHOUT |
03/02/2009 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 1 1/4 FROM METER THRU RPB INTO BLD. OK PLEASE SEE NOTE #3 FROM 12/24/08 INSPECTION & COMPLY IF YOU DESIRE PROMPT INSPECTIONS (GEN. CONTRACTOR) |
03/09/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* ENSURE ALL PENETRATIONS THROUGH 2 HOUR FIRE WALL ARE PROPERLY FIRE CAULKED |
03/24/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO SET CEILING TILES |
03/24/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
04/06/2009 | ELECTRIC - PROGRESS | RMORENO | Approved | IVRS - Inspection :* |
04/07/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER R. MORENO |
04/08/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
04/09/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
04/10/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
04/17/2009 | NPPO - FINAL | ACONNOR | Approved | |
04/17/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/17/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
04/17/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
04/17/2009 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
04/17/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
04/17/2009 | FIRE - FINAL | LTHOMAS | Approved | |
04/17/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
04/21/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
04/21/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
04/21/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
04/21/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
04/27/2009 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
05/01/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
05/04/2009 | PERMIT FINALED | BFLORES | Approved |