Apply Date:
08/01/2008
Applicant:
N/A
Description:
NEW: MIDDLE SCHOOL (ADMIN BUILDING) BUILDING 1 PER PLANS
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T08CM02656
Permit Status: C of o
Permit Description: NEW: MIDDLE SCHOOL (ADMIN BUILDING) BUILDING 1 PER PLANS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/01/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 05/08/2009 | COMPLETED |
07/16/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 07/16/2009 | COMPLETED |
08/01/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 08/01/2008 | COMPLETED |
08/01/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/17/2008 | COMPLETED |
09/17/2008 | POST 3RD PARTY REVIEW | 09/19/2008 | COMPLETED |
09/19/2008 | POST 3RD PARTY REVIEW | 10/01/2008 | COMPLETED |
10/01/2008 | POST 3RD PARTY REVIEW | 10/06/2008 | COMPLETED |
12/18/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 12/22/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02656
Permit Status: C of o
Permit Description: NEW: MIDDLE SCHOOL (ADMIN BUILDING) BUILDING 1 PER PLANS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/01/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02656
Permit Description: NEW: MIDDLE SCHOOL (ADMIN BUILDING) BUILDING 1 PER PLANS
Total Completed Inspections - 43
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/20/2008 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* CMU STEM WALL @ GRID LINE FROM A.0 TO G.0/1.0 TO 3.0 0 TO 45' EAST OF 1.0/40' NORTH G.0 - 0 TO 45' EAST OF 2.0/40' NORTH OF G.0 |
10/24/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST THRU BLD. TO 2-WAY CLEANOUT OK |
10/28/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 2" T/K STUB UP & OUT OF BLD. OK |
10/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
11/07/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* MAIN BLDG. PAD |
11/07/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
11/12/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* 3/4" IN WALL COPPER PRE-FAB TEST ROOMS #102 & 114 & 119 |
11/12/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* 1. OK UFER GROUNDS FOR SERVICE & TELEPHONE 2. OK U.G FOR 2 FLOOR BOXES |
11/24/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
12/04/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
12/04/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* STEEL REINFORCEMENT OF CMU WALLS @ 30' WEST OF B.0 TO C.0/1.0 AND BOUND WITHIN 2' TO 5' NORTH OF B.0 FROM 12'0" TO 15'4" AFFE |
01/12/2009 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
01/21/2009 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* FINISH BOLTING AND NAILING |
01/22/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
01/30/2009 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
04/02/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
04/03/2009 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
04/07/2009 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* OFFSET FOR WATER HEATER TO BE 60 DEG. FOR MATERIAL TYPE USED |
04/07/2009 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
04/08/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
04/08/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
04/08/2009 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
05/29/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* STERILIZATION AND BACTERIA REPORT OK |
05/29/2009 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
06/09/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* AIR BALANCE OK |
06/09/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/09/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | |
06/26/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
06/29/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
06/29/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
07/01/2009 | BUILDING - PROGRESS | GDABBS | Approved | |
07/01/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
07/01/2009 | ENGINEERING - FINAL | JFEMLING | Approved | Approved, call in for final grading inspection |
07/01/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
07/02/2009 | FIRE - LANE SIGNS | LTHOMAS | Approved | |
07/09/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
07/09/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
07/09/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
07/09/2009 | FIRE - FINAL | LTHOMAS | Approved |