Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Apply Date:
06/03/2008
Applicant:
N/A
Description:
NEW: APARTMENT BUILDING #11
Contractors:
  • K AND S II LIMITED ,

Permit Reviews

Permit Number - T08CM01836
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #11
Start Date Submittal Complete Date Status  
06/03/2008 PLANS OK TO SUBMIT - 3RD PARTY 06/04/2008 COMPLETED Review Details
06/04/2008 3RD PARTY REVIEW-COMMERCIAL 09/08/2008 COMPLETED Review Details
09/08/2008 POST 3RD PARTY REVIEW 10/06/2008 COMPLETED Review Details
12/15/2008 RESUBMITTAL 04/07/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM01836
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #11
Total Outstanding Activity Conditions - 1
Date Name
06/03/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM01836
Permit Description: NEW: APARTMENT BUILDING #11
Total Completed Inspections - 44
Date Description Inspector Results Comments
10/23/2009 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
10/26/2009 PLUMBING - SEWER HCS CONNECT BBENEDON Approved IVRS - Inspection :*
10/29/2009 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
1) UFER AND EMT 3/4 FOR ISLAND OK
10/29/2009 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
1) OK TO POUR SLAB
10/29/2009 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
1) CONTINOUS FOOTINGS WITH POST TENSION SYSTEM OK TO POUR FOOTINGS
10/29/2009 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
10/29/2009 ELECTRIC - UNDERGROUND RMORENO Approved IVRS - Inspection :*
11/20/2009 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
1) TWO HOSE BIBS OK-INSTALL AVB
11/30/2009 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO DRY IN ROOF SYSTEM
11/30/2009 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
1) CLIPS AND SHEATHING INSTALLED PER PLANS
12/11/2009 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/21/2009 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
1) WEST STAIRS-FOOTINGS-OK TO POUR
12/30/2009 ELECTRIC - CABLE DROP RMORENO Approved IVRS - Inspection :*
02/19/2010 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
1) OK FOR SHEETROCK MECHANICAL ONLY
02/19/2010 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
1) WALLS IN BLDG ALL OK
02/19/2010 U VALUE FOR WINDOW GDABBS Approved IVRS - Inspection :*
02/19/2010 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
02/19/2010 FRAMING GDABBS Approved IVRS - Inspection :*
02/26/2010 STUCCO MESH JBURGE Approved IVRS - Inspection :*
1) OK TO STUCCO EXTERIOR WALLS
03/04/2010 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
04/27/2010 NPPO - FINAL ACONNOR Approved
04/30/2010 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved IVRS - Inspection :*
1) #11101 thru 11104 & 11201 thru 11204 GROUNDING AND BONDING ALL OK
05/03/2010 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED FOR BLDG 11: #11101 THRU 11104 & 11201 THRU 11204 PER R. MORENO
05/24/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
05/24/2010 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
05/24/2010 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
05/24/2010 SIGN - FINAL JYBARRA Approved
05/25/2010 RIGHT OF WAY - FINAL MCASTRO Approved
06/01/2010 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
06/08/2010 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
06/15/2010 FIRE - HYDRANTS LTHOMAS Approved
06/15/2010 FIRE SPKLR - FINAL LTHOMAS Approved
06/15/2010 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
06/15/2010 FIRE - FINAL LTHOMAS Approved
06/17/2010 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
06/17/2010 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
06/22/2010 LANDSCAPE - FINAL MRUSSO Approved
06/22/2010 ENGINEERING - FINAL MRUSSO Approved
12/10/2010 OUTDOOR LIGHTING FINAL RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - PROGRESS RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - CONSTRUCTION POWER RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - ABOVE CEILING RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - TEMPORARY SERVICE RMORENO Approved PER EL FINAL