Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Apply Date:
06/03/2008
Applicant:
N/A
Description:
NEW: APARTMENT BUILDING #5
Contractors:
  • K AND S II LIMITED ,

Permit Reviews

Permit Number - T08CM01830
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #5
Start Date Submittal Complete Date Status  
06/03/2008 PLANS OK TO SUBMIT - 3RD PARTY 06/03/2008 COMPLETED Review Details
06/03/2008 3RD PARTY REVIEW-COMMERCIAL 09/08/2008 COMPLETED Review Details
09/08/2008 POST 3RD PARTY REVIEW 10/06/2008 COMPLETED Review Details
12/15/2008 RESUBMITTAL 04/07/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM01830
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #5
Total Outstanding Activity Conditions - 1
Date Name
06/03/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM01830
Permit Description: NEW: APARTMENT BUILDING #5
Total Completed Inspections - 44
Date Description Inspector Results Comments
07/29/2009 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
08/12/2009 ELECTRIC - UNDERGROUND RMORENO Approved IVRS - Inspection :*
1) ISLAND POWER 3/4 PVC OK
08/17/2009 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
1) UFER OK
08/18/2009 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
1) CONTINOUS FOOTINGS OK TO POUR (SOUTH)
08/18/2009 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
1) POST TENSION SYSTEM PER PLANS OK TO POUR (SOUTH)
09/15/2009 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO DRY IN ROOF SYSTEM
09/15/2009 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
1) SHEATHING AND CLIPS IN PLACE PER PLANS
10/01/2009 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
10/02/2009 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
10/07/2009 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
10/14/2009 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
10/28/2009 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
1) LETTER RECEIVED TO DELETE RPS AT BLDG SERVICES
10/28/2009 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
10/30/2009 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) OK FOR SHEETROCK
10/30/2009 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
11/17/2009 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
1) WALLS AND CEILINGS OK (ELECTRICAL)
11/18/2009 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
1) U VALUES .39-.52
11/18/2009 FRAMING JBURGE Approved IVRS - Inspection :*
1) OK TO SHEETROCK
11/18/2009 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
12/03/2009 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*OK TO POUR STAIRWELL FOOTING
12/14/2009 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
12/15/2009 ELECTRIC - TEMPORARY SERVICE JJAWORSKY Approved IVRS - Inspection :
See detailed listing on site.| 999*
1) MUST POST BOND FIRST
01/05/2010 STUCCO MESH JBURGE Approved IVRS - Inspection :*
1) OK TO STUCCO
03/26/2010 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved IVRS - Inspection :*
03/29/2010 TEP CLEARANCE - AM JWEATHER Approved INCR CLEARED FOR 1ST FLOOR: 5101,5102,5103 & 5104 AND 2ND FLOOR: 5201,5202,5203 & 5204 PER R. MORENO
04/19/2010 SIGN - FINAL JYBARRA Approved
04/27/2010 NPPO - FINAL ACONNOR Approved
04/30/2010 FIRE SPKLR - FINAL LTHOMAS Approved
04/30/2010 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
1) 5101,5102,5103,5104,5201,5202,5203 AND 5204 GFI'S KITCHEN, SMOKE DETECTORS AND POWER LIGHTING ALL OK
05/03/2010 FIRE - HYDRANTS LTHOMAS Approved
05/03/2010 FIRE - FINAL LTHOMAS Approved
05/06/2010 OUTDOOR LIGHTING FINAL RMORENO Approved IVRS - Inspection :*
05/06/2010 ELECTRIC - PROGRESS RMORENO Approved IVRS - Inspection :*
05/06/2010 ELECTRIC - CONSTRUCTION POWER RMORENO Approved IVRS - Inspection :*
05/10/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
05/10/2010 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
05/10/2010 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
05/10/2010 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
06/22/2010 LANDSCAPE - FINAL MRUSSO Approved
06/22/2010 ENGINEERING - FINAL MRUSSO Approved
07/22/2010 RIGHT OF WAY - FINAL PWhiddon Approved
12/10/2010 ELECTRIC - CABLE DROP RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - ABOVE CEILING RMORENO Approved
12/10/2010 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved PER EL FINAL