Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Apply Date:
06/03/2008
Applicant:
N/A
Description:
NEW: APARTMENT BUILDING #4
Contractors:
  • K AND S II LIMITED ,

Permit Reviews

Permit Number - T08CM01829
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #4
Start Date Submittal Complete Date Status  
06/03/2008 PLANS OK TO SUBMIT - 3RD PARTY 06/04/2008 COMPLETED Review Details
06/04/2008 3RD PARTY REVIEW-COMMERCIAL 09/08/2008 COMPLETED Review Details
09/08/2008 POST 3RD PARTY REVIEW 10/06/2008 COMPLETED Review Details
12/15/2008 RESUBMITTAL 04/07/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM01829
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #4
Total Outstanding Activity Conditions - 1
Date Name
06/03/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM01829
Permit Description: NEW: APARTMENT BUILDING #4
Total Completed Inspections - 44
Date Description Inspector Results Comments
07/27/2009 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
08/12/2009 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
1) PRE-SLAB OK
08/12/2009 ELECTRIC - UNDERGROUND RMORENO Approved IVRS - Inspection :*
1) ISLAND POWER 3/4 PVC OK
08/17/2009 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
1) UFER OK
08/18/2009 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
1) POST TENSION SYSTEM PER PLANS OK TO POUR (SOUTH)
08/18/2009 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved IVRS - Inspection :*
1) CONTINOUS FOOTINGS-OK TO POUR (SOUTH)
09/30/2009 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO DRY IN
09/30/2009 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
1) SHEATHING AND CLIPS IN PLACE AS PER PLANS
10/07/2009 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
10/16/2009 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1) OK FOR PRE-SHEET ROCK
10/30/2009 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
11/05/2009 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
1) INSTALL 2 CLIPS ON VERTICALS IN STUDS
2) DWV AND DOMESTIC TESTS OK
3) OK TO COVER
11/05/2009 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
11/17/2009 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) OK FOR SHEETROCK
11/17/2009 ELECTRIC - INTERMEDIATE RMORENO Approved IVRS - Inspection :*
1) WALLS AND CEILINGS OK
11/18/2009 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
1) U-VALUES AT .39-.52
11/18/2009 FRAMING JBURGE Approved IVRS - Inspection :*
1) OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES
11/18/2009 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
11/30/2009 BUILDING - PROGRESS JBURGE Approved 1) STAIR FOOTINGS OK TO POUR
11/30/2009 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
12/08/2009 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
1) 4 WEST SIDE UNITS ARE COMPLETE-OK TO TAPE THROUGHOUT
12/15/2009 ELECTRIC - TEMPORARY SERVICE JJAWORSKY Approved IVRS - Inspection :
See detailed listing on site.| 999*
1) MUST POST BOND FIRST
12/17/2009 STUCCO MESH JBURGE Approved IVRS - Inspection :*
1) OK TO STUCCO
03/26/2010 ELECTRIC - TEMP POWER FOR TEST RMORENO Approved IVRS - Inspection :*
03/29/2010 TEP CLEARANCE - AM JWEATHER Approved INCR CLEARED FOR 1ST FLOOR: 4101,4102,4103 & 4103 AND 2ND FLOOR: 4201,4202,4203 & 4204 PER R. MORENO
04/19/2010 SIGN - FINAL JYBARRA Approved
04/27/2010 NPPO - FINAL ACONNOR Approved
04/30/2010 FIRE SPKLR - FINAL LTHOMAS Approved
04/30/2010 ELECTRIC - FINAL RMORENO Approved IVRS - Inspection :*
1) GFI KITCHEN, ARC FAULTS, SMOKE ALARMS, DETECTORS AND PANELS LABELED 4101,4102,4103,4104,4201,4202,4203 AND 4204
05/03/2010 FIRE - FINAL LTHOMAS Approved
05/03/2010 FIRE - HYDRANTS LTHOMAS Approved
05/06/2010 PLUMBING - SEWER HCS CONNECT BBENEDON Approved
05/06/2010 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
05/06/2010 OUTDOOR LIGHTING FINAL RMORENO Approved IVRS - Inspection :*
05/06/2010 ELECTRIC - OUTDOOR LIGHTING RMORENO Approved IVRS - Inspection :*
05/06/2010 ELECTRIC - PROGRESS RMORENO Approved IVRS - Inspection :*
05/06/2010 ELECTRIC - CONSTRUCTION POWER RMORENO Approved IVRS - Inspection :*
05/10/2010 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
05/10/2010 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
05/26/2010 ENGINEERING - FINAL MRUSSO Approved
06/22/2010 LANDSCAPE - FINAL MRUSSO Approved
07/22/2010 RIGHT OF WAY - FINAL PWhiddon Approved
12/10/2010 ELECTRIC - CABLE DROP RMORENO Approved PER EL FINAL
12/10/2010 ELECTRIC - ABOVE CEILING RMORENO Approved PER EL FINAL

Documents

File Name Document Type  
C OF O_12-10-2010.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW