Permit: T08CM01827
Permit Details
Apply Date:
06/03/2008
Applicant:
N/A
Description:
NEW: APARTMENT BUILDING #2
Contractors:
- K AND S II LIMITED ,
Permit Reviews
Permit Number - T08CM01827
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #2
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/03/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 06/04/2008 | COMPLETED |
06/04/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/08/2008 | COMPLETED |
08/10/2009 | REVISION - - 1ST | 08/10/2009 | COMPLETED |
09/08/2008 | POST 3RD PARTY REVIEW | 10/06/2008 | COMPLETED |
12/15/2008 | RESUBMITTAL | 04/07/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM01827
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING #2
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/03/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM01827
Permit Description: NEW: APARTMENT BUILDING #2
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/25/2009 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* 1. OK 2/0 UFER TO REBAR IN FOOTING 2. OK 3/4" PVC TO KITCHEN ISLAND |
06/25/2009 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
06/25/2009 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
06/26/2009 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* 1) BLDG PAD CERT, BLDG PAD COMPACTION AND POST TENSION SLAB 2) SPECIAL INSPECTED BY LEAD STAR AND SHANE LAND SURVEYING IN COMPLIANCE |
07/30/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY-IN TRUSS CALCS ON SITE |
07/30/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO COVER - STRAPS & HOLD-DOWNS IN PLACE OK TO COVER |
08/19/2009 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
08/27/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* 1) MASTER CLOSET AND BATH CEILINGS-OK 2) UTILITY ROOM AND PANTRY OK |
09/29/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR SHEETROCK |
09/29/2009 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
09/29/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
10/01/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
10/02/2009 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
10/05/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SHEETROCK |
10/06/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 1) RETAINING WALL FOOTING (NORTH SIDE) OK TO POUR-DETAIL #08-103, 2/10/09 |
10/15/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) BLDG #2 SERVICE WIRES OK |
10/21/2009 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
11/04/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
11/13/2009 | ELECTRIC - CABLE DROP | RMORENO | Approved | 1) LADERAL TO METER BASE OK |
11/17/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) WEST STAIRWELL FOOTING-OK TO POUR |
12/04/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO |
12/11/2009 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
12/15/2009 | ELECTRIC - TEMPORARY SERVICE | JJAWORSKY | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) MUST POST BOND FIRST |
12/15/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
03/05/2010 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
03/05/2010 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
03/09/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #2101,2102,2103,2104,2201,2202,2203 & 2204 PER R. JIROUDEK-SENT OVER TO TEP ON 03/08/10 IN THE AM PER D. ROBEY |
03/26/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
03/26/2010 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
03/26/2010 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | |
03/26/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
04/08/2010 | FIRE - HYDRANTS | LThomas | Approved | Approved 4/8/10 |
04/08/2010 | FIRE SPKLR - FINAL | LThomas | Approved | Approved 4/8/10 |
04/08/2010 | FIRE - FINAL | LThomas | Approved | Approved 4/8/10 |
04/12/2010 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
04/19/2010 | PLUMBING - PRE SLAB | GDABBS | Approved | |
04/19/2010 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | |
04/19/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
04/19/2010 | SIGN - FINAL | JYBARRA | Approved | |
04/27/2010 | NPPO - FINAL | ACONNOR | Approved | |
05/27/2010 | LANDSCAPE - FINAL | MRUSSO | Approved | |
05/27/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
07/22/2010 | RIGHT OF WAY - FINAL | PWhiddon | Approved | |
12/10/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LThomas | Approved |