Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL OTHER
Apply Date:
04/28/2008
Applicant:
N/A
Description:
TI: OFFICE
Contractors:
  • HAZEN LTD , STEVE

Permit Reviews

Permit Number - T08CM01351
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date Submittal Complete Date Status  
04/28/2008 COMMERCIAL TI 04/30/2008 COMPLETED Review Details
04/30/2008 RESUBMITTAL 05/01/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM01351
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
04/28/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM01351
Permit Description: TI: OFFICE
Total Completed Inspections - 18
Date Description Inspector Results Comments
05/05/2008 PLUMBING - ROUGH, SOIL RRICH Approved WATER TEST FROM UNDERGROUND TO EXISTING VENT OK
CAP OF OLD LAV LOCATION OK DWV
05/08/2008 FRAMING JBURGE Approved IVRS - Inspection :*
OK TO SHEETROCK PENDING ELECTRIC AND PLUMBING INTERMEDIATES
05/09/2008 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
WATER TO LAV OK
05/12/2008 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
05/16/2008 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1. ON FINAL PROVIDE AIR BALANCE REPORT
2. DRAWINGS NEED TO SHOW REQUIRED CFM's AT ALL SUPPLY DIFFUSERS
3. OK FOR CEILING TILES
05/16/2008 ELECTRIC - ABOVE CEILING RJIROUDE Approved IVRS - Inspection :*
05/16/2008 ELECTRIC - INTERMEDIATE RJIROUDE Approved IVRS - Inspection :*
05/20/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
05/20/2008 FIRE - FINAL LTHOMAS Approved
05/20/2008 FIRE SPKLR - FINAL LTHOMAS Approved
05/21/2008 ELECTRIC - FINAL RJIROUDE Approved IVRS - Inspection :*
05/22/2008 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
05/22/2008 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
05/22/2008 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
05/22/2008 PLUMBING - PROGRESS RRICH Approved IVRS - Inspection :*
05/27/2008 ENGINEERING - FINAL DROBERTS Approved DROVE OUT TO THE SITE AND LOOKED OVER THE WORK THAT IS BEING COMPLETED FOR THIS SITE. ALL OF THE WORK IS LOCATED WITHIN THE FOUR WALLS OF THE SITE AND DOES NOT REQUIRE THAT ANYTHING IS INSPECTED BY THE ENGINEERING DEPARTMENT. PAPER WORK WILL BE DELIVERED BACK OUT TO THE SITE TOMORROW MORNING FOR THEIR RECORDS.
05/27/2008 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
06/06/2008 RIGHT OF WAY - FINAL MCASTRO Approved

Documents

File Name Document Type  
C OF O_06-06-2008.TIF CERT OF OCC VIEW
TEMP C OF O_05-23-2008.TIF CERT OF OCC VIEW
001_G-1.TIF CONSTRPLANS VIEW
002_D-1.TIF CONSTRPLANS VIEW
003_A-1.TIF CONSTRPLANS VIEW
004_A-2.TIF CONSTRPLANS VIEW
005_M-1.TIF CONSTRPLANS VIEW
006_P-1.TIF CONSTRPLANS VIEW
007_E1.TIF CONSTRPLANS VIEW
008_E2.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW