Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM00917
Permit Details
Apply Date:
03/19/2008
Applicant:
RICHARD G GREEN
Description:
PARKING AND NEW BASEBALL FIELD
Architects:
- GREEN, RICHARD G
Contractors:
- ANDERSON CONSTRUCTION CORP , M
Permit Reviews
Permit Number - T08CM00917
Permit Status: Final
Permit Description: PARKING AND NEW BASEBALL FIELD
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/19/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 03/20/2008 | COMPLETED |
03/19/2008 | PLANS OK TO SUBMIT - SITE | 03/19/2008 | COMPLETED |
03/20/2008 | 3RD PARTY REVIEW-COMMERCIAL | 05/02/2008 | COMPLETED |
03/20/2008 | SITE | 05/02/2008 | COMPLETED |
05/02/2008 | POST 3RD PARTY REVIEW | 05/22/2008 | COMPLETED |
05/02/2008 | SITE | 05/22/2008 | COMPLETED |
06/05/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 06/10/2008 | COMPLETED |
11/17/2008 | POST 3RD PARTY REVIEW | 11/18/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00917
Permit Status: Final
Permit Description: PARKING AND NEW BASEBALL FIELD
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/19/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00917
Permit Description: PARKING AND NEW BASEBALL FIELD
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
07/10/2008 | SEPTIC - SYSTEM | BBENEDON | Approved | IVRS - Inspection :* 1. THE SEPTIC SYSTEM SHALL BE INSPECTED BY PIMA COUNTY 2. THE SITE SEWER HOWEVER REQUIRES CITY INSPECTION 3. PLEASE HAVE SEWER PRE-CONSTRUCTION MEETING AND SITE SEWER ADDED TO YOUR PERMIT 4. CALL FOR PRE-CONST. INSP. AND COORDINATE TO HAVE CONTRACTOR, ENGINEER AND CITY INSPECTION AT MEETING 5. EXPOSE PIPING COVERED W/OUT INSPECTION |
07/15/2008 | SEWER - PRE CONSTRUCTION MTG | RRICH | Approved | IVRS - Inspection :* MEETING WITH HARRY & ADAM OF GREEN RIDGE CONST. JACK & RON - ANDERSON BON - RS ENGINEERING TRINI - WILDAN SEWER TO BE EXPOSED, AT MANHOLE AND CHANGE OF DIRECTION WITH CLEANOUT EXPOSED, AIR TESTED OF SEWER, VACUUM TEST OF NEW MANHOLE WITH CORRECT COUPLING BETWEEN MANHOLE & SEPTIC TANK AND TEST ON THIS SECTION AT LATER DATE. CONTRACTOR TO PROVIDE ACTUAL SEWER FLOW SURVEY FROM LICENSED SURVEYING COMPANY |
10/01/2008 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
10/08/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 1" PVC SCH 40 FROM POINT OF CONNECTION TO RPB FOR LANDSCAPING, WITH 1/2" DRINKING FOUNTAIN SUPPLY TIED INTO 1/2" COPPER AT EQUESTRIAN CENTER |
10/09/2008 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) DRYWALL INSTALLED AT THIS SITE 2) APPROVED TIED INTO BLDG |
10/21/2008 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK GROUND RODS - SERVICE & POLES OK 1 1/2" PVC FOR IRRIGATION CONTROLS |
10/21/2008 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
10/21/2008 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
12/23/2008 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* RECEIVED BACTERIA REPORT, PCDEQ AUTHORIZATION TO DISCHARGE ON SITE. |
12/23/2008 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
04/06/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR 1M & 2M PER D. SANTACRUZ |
04/23/2009 | ELECTRIC - CABLE DROP | DSANTACR | Approved | |
04/23/2009 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
04/23/2009 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
04/23/2009 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
04/23/2009 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
04/23/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
08/06/2009 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
08/07/2009 | PERMIT FINALED | JWEATHER | Approved |