Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM00138
Permit Details
Apply Date:
01/15/2008
Applicant:
PRESIDIO CONSTRUCTION COMPANY
Description:
TI:RETAIL - SUITE 100
Contractors:
- PRESIDIO CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T08CM00138
Permit Status: C of o
Permit Description: TI:RETAIL - SUITE 100
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/15/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 01/16/2008 | COMPLETED |
01/16/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 03/07/2008 | COMPLETED |
03/07/2008 | POST 3RD PARTY REVIEW | 03/07/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00138
Permit Status: C of o
Permit Description: TI:RETAIL - SUITE 100
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/15/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM00138
Permit Description: TI:RETAIL - SUITE 100
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/18/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
03/18/2008 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED FOR #100 PER D. SANTACRUZ |
03/20/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
03/28/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
04/02/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
04/02/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
04/11/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
04/11/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
04/12/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
04/21/2008 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
04/28/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
04/28/2008 | SIGN - FINAL | ACONNOR | Approved | N/A |
04/28/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
04/28/2008 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
04/28/2008 | FIRE - FINAL | CSCHULTZ | Approved | |
04/29/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
04/29/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* BALANCE REPORT OK |
04/29/2008 | ENGINEERING - FINAL | MAVERY | Approved | keep all construction debris separated from public access |
04/29/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
04/29/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
04/29/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
05/01/2008 | PERMIT FINALED | MHENSON | Approved | |
05/01/2008 | NPPO - FINAL | ACONNOR | Approved | N/A |
05/01/2008 | BUILDING - FINAL | MHENSON | Approved | |
05/01/2008 | PLUMBING - FINAL | RLEDONNE | Approved | |
05/01/2008 | FIRE - ALARM FINAL | CSCHULTZ | Approved |