Apply Date:
01/02/2008
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW SHELL BLDG
Architects:
- PIERSON, JORGE ANDRES
Contractors:
- GILES CONSTRUCTION INC
Permit Reviews
Permit Number - T08CM00002
Permit Status: Final
Permit Description: NEW SHELL BLDG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/02/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 01/03/2008 | COMPLETED |
01/03/2008 | 3RD PARTY REVIEW-COMMERCIAL | 03/24/2008 | COMPLETED |
03/24/2008 | POST 3RD PARTY REVIEW | 04/24/2008 | COMPLETED |
04/24/2008 | RESUBMITTAL | 06/09/2008 | COMPLETED |
07/31/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 08/20/2008 | COMPLETED |
08/26/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 09/11/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00002
Permit Status: Final
Permit Description: NEW SHELL BLDG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/02/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00002
Permit Description: NEW SHELL BLDG
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/07/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
07/10/2008 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* GRID LINE A-B-4 1.0 - 2.0 |
07/15/2008 | ELECTRIC - TEMPORARY POLE | DSANTACR | Approved | IVRS - Inspection :* |
09/04/2008 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* TRASH ENCLOSURE OK |
09/10/2008 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* TRASH ENCLOSURE OK TO TOP OUT ALREADY GROUTED ACCEPTED SPECIAL 1. WESTERN TECH. SPECIAL INSPECTED 3 HINGE PLATES INSTEAD OF 4 |
09/10/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* OK TO DRY IN MAIN BLDG. NAILING GOOD |
09/10/2008 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
09/17/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
09/18/2008 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
09/18/2008 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
09/24/2008 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
09/25/2008 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
10/10/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
10/22/2008 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
10/27/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* UNDER CHLORINATION IN PROCESS UNABLE TO TEST SINK |
10/27/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
10/27/2008 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
10/27/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
10/28/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
10/28/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/28/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
10/29/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* SHELL ONLY |
11/19/2008 | NPPO - FINAL | ACONNOR | Approved | |
11/19/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
11/20/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
11/21/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "HOUSE PANEL" PER D. SANTACRUZ |
12/03/2008 | ELECTRIC - RECONNECT | DSANTACR | Approved | IVRS - Inspection :* |
12/03/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
12/03/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
12/05/2008 | ELECTRIC - UFER | DSANTACR | Approved | |
12/05/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
12/05/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
12/05/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
02/05/2009 | FIRE - FINAL | LTHOMAS | Approved | |
02/09/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
05/21/2009 | ENGINEERING - FINAL | MCARREON | Approved | |
05/22/2009 | BUILDING - FINAL | MHENSON | Approved |