Permit: T08BU00251
Permit Details
Apply Date:
02/08/2008
Applicant:
PSOMAS
Description:
GRADING:
Contractors:
- TROON CONSTRUCTION L L C
Permit Reviews
Permit Number - T08BU00251
Permit Status: Final
Permit Description: GRADING:
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/27/2009 | RESUBMITTAL - GRADING ALL | 02/02/2009 | COMPLETED |
02/08/2008 | PLANS OK TO SUBMIT - GRADING | 02/08/2008 | COMPLETED |
02/08/2008 | GRADING | 04/22/2008 | COMPLETED |
04/22/2008 | RESUBMITTAL - GRADING ALL | 05/19/2008 | COMPLETED |
05/28/2008 | RESUBMITTAL - GRADING | 06/11/2008 | COMPLETED |
06/11/2008 | RESUBMITTAL - GRADING | 06/23/2008 | COMPLETED |
07/21/2009 | REVISION - GRADING | 07/29/2009 | COMPLETED |
07/29/2009 | REVISION - GRADING | 07/29/2009 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T08BU00251
Permit Status: Final
Permit Description: GRADING:
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/08/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08BU00251
Permit Description: GRADING:
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/24/2008 | STORMWATER FOLLOW-UP INSP | NKALAHAR | Approved | SITE WORK CONTINUING NO CONCERNS |
07/20/2009 | GRADING - TIER REV | PGEHLEN | Approved | Received e-mail from PSOMAS (Engineer of Record). In addition to the two ada ramps west of the building, 4 additional scubbers have been added to the site and contactor wants to replace some rip rap with a planter wall. I believe these are all Tier 1 and can be done on the grading plan. I will let the Engineer of Record know. |
08/31/2009 | STORMWATER INSTALL OF CONTROLS | JFEMLING | Approved | Site is landscaped and stable. |
08/31/2009 | GRADING - INTERMEDIATE | JFEMLING | Approved | Finish all site work, call for final inspection, provide final grading plan (as-built), provide eng. cert for drainage. removce all construction debris and temp storage trailers. |
09/01/2009 | GRADING - FINAL | JFEMLING | Approved | Complete the following and call for re-inspection. 1) Install all HC signs 2) Install all bike parking 3) Remove rock from sidewalk scuppers to allow water to flow freely. 4) Install hole to lock open dumpster gate. 5) Install curb header around planters at rear of building. 6) Provide as-built drawings 7) emove all construction debris and temporary storage trailers and roll offs. |
06/17/2010 | ENGINEERING PRE-CONSTRUCTION | JFEMLING | Approved | |
06/17/2010 | NPPO PRE PERMIT INSPECTION | JFEMLING | Approved | |
06/17/2010 | LANDSCAPE INSPECTION | JFEMLING | Approved | |
06/17/2010 | GRADING - CHECK FOR ACTIVITY | JFEMLING | Approved |