Permit: T08BU00251

Parcel: 13423424B


Addresses:

251 S WILMOT RD

Inspection Status: Approved

Inspection History: STORMWATER INSTALL OF CONTROLS

Date Description Inspector Results Comments
08/31/2009 STORMWATER INSTALL OF CONTROLS Approved Site is landscaped and stable.
08/13/2008 STORMWATER INSTALL OF CONTROLS Partial Approval NO CREW ON SITE
WATTLE IN PLACE ALONG PERIMETER OF SITE
07/28/2008 STORMWATER INSTALL OF CONTROLS Partial Approval JIM ALLEN 480-304-1225 SITE SUPERINTENDENT
CHRIS 271-1720 DAALCO CONSTRUCTION GRADING SUPER.
1. STRAW WATTLE HAS BEEN INSTALLED AROUND PERIMETER OF SITE.
2. 1" GRAVEL HAS BEEN PLACED ON THE CONSTRUCTION.
ENTRANCE.
3. SWEEP ADJACENT PAVEMENT AS NEEDED TO CONTROL TRACKOUT.
NICHOLE ZORMEIER WILL CONDUCT THE PRE-CONSTRUCTION INSPECTION TOMORROW.