Permit: T07CM04662
Permit Details
Apply Date:
12/12/2007
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW METAL SHELL BUILDING
Architects:
- ARMSTRONG, TERRY
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T07CM04662
Permit Status: Final
Permit Description: NEW METAL SHELL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2008 | 3RD PARTY REVIEW-COMMERCIAL | 01/03/2008 | COMPLETED |
| 01/03/2008 | POST 3RD PARTY REVIEW | 01/10/2008 | COMPLETED |
| 12/12/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 01/03/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM04662
Permit Status: Final
Permit Description: NEW METAL SHELL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/12/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM04662
Permit Description: NEW METAL SHELL BUILDING
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2008 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
| 07/02/2008 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 07/02/2008 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 07/02/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 07/17/2008 | ELECTRIC - UFER | GDABBS | Approved | IVRS - Inspection :* |
| 07/21/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
| 07/21/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 11/12/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* 2ND LAYER @ INSIDE & OUTSIDE OF FIREWALL |
| 07/02/2009 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/19/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) WATER DISTRIBUTION FROM 10' FROM METER THRU BLDG OK |
| 12/04/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 11/01/2010 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 11/09/2010 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 12/06/2010 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/07/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
| 12/28/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 12/28/2010 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 12/28/2010 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 12/28/2010 | SIGN - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 12/28/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/28/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 01/27/2011 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/27/2011 | FIRE - FINAL | CSCHULTZ | Approved | |
| 03/22/2011 | NPPO - FINAL | DROBERTS | Approved | THIS SITE HAS BEEN CHECKED FOR THE FULL RELEASE OF THE BUILDING SHELL. THIS IS APPROVED AT THIS TIME FOR THE SHELL BUILDING ONLY, AND ITEMS THAT ARE NOT COMEPLETE AT THIS TIME WILL BE HELD TO THE COMBO PERMIT AND WILL BE RE-INSPECTED ONCE ALL WORK HAS BEEN COMPLETED. MISSING LANDSCAPING, AND ENGINEERING ASPECTS NOT COMPLETE AT THIS TIME. |
| 03/22/2011 | LANDSCAPE - FINAL | DROBERTS | Approved | THIS SITE HAS BEEN CHECKED FOR THE FULL RELEASE OF THE BUILDING SHELL. THIS IS APPROVED AT THIS TIME FOR THE SHELL BUILDING ONLY, AND ITEMS THAT ARE NOT COMEPLETE AT THIS TIME WILL BE HELD TO THE COMBO PERMIT AND WILL BE RE-INSPECTED ONCE ALL WORK HAS BEEN COMPLETED. MISSING LANDSCAPING, AND ENGINEERING ASPECTS NOT COMPLETE AT THIS TIME. |
| 03/22/2011 | ENGINEERING - FINAL | DROBERTS | Approved | THIS SITE HAS BEEN CHECKED FOR THE FULL RELEASE OF THE BUILDING SHELL. THIS IS APPROVED AT THIS TIME FOR THE SHELL BUILDING ONLY, AND ITEMS THAT ARE NOT COMEPLETE AT THIS TIME WILL BE HELD TO THE COMBO PERMIT AND WILL BE RE-INSPECTED ONCE ALL WORK HAS BEEN COMPLETED. MISSING LANDSCAPING, AND ENGINEERING ASPECTS NOT COMPLETE AT THIS TIME. |
| 05/19/2011 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |