Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/04/2009 | FRAMING | Approved | IVRS - Inspection :* | |
| 09/02/2009 | FRAMING | Not ready for Inspection | IVRS - Inspection :* | |
| 08/26/2009 | FRAMING | Partial Approval | IVRS - Inspection :* 1) REINFORCEMENT STEEL AT FOOTING FOR TRASH ENCLOSURE AND BLDG SLAB OK |
|
| 11/14/2008 | FRAMING | Partial Approval | IVRS - Inspection :* 2 LAYERS OF 5/8" DRYWALL @ EXTERIOR SIDE OF FIREWALL |
|
| 11/12/2008 | FRAMING | Not ready for Inspection | IVRS - Inspection :* | |
| 11/07/2008 | FRAMING | Not ready for Inspection | IVRS - Inspection :* 1ST LAYER AT FIREWALL ONLY NOTE: SECOND LAYER TO BE OFFSET AT SEAMS FROM FIRST LAYER SEAMS |
|
| 10/30/2008 | FRAMING | Partial Approval | IVRS - Inspection :* HAT CHANNEL FOR FIRE WALL |