Permit: T07CM04456
Permit Details
Apply Date:
11/26/2007
Applicant:
CHONIS, GUS WILLIAM
Description:
ADDITION:BATHROOM R1 Replace Gaspack & new Gas pipe
Architects:
- CHONIS, GUS WILLIAM
Permit Reviews
Permit Number - T07CM04456
Permit Status: Final
Permit Description: ADDITION:BATHROOM
R1 Replace Gaspack & new Gas pipe
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/29/2008 | REVISION - - 1ST | 01/29/2008 | COMPLETED |
| 11/26/2007 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 11/26/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM04456
Permit Status: Final
Permit Description: ADDITION:BATHROOM
R1 Replace Gaspack & new Gas pipe
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/26/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM04456
Permit Description: ADDITION:BATHROOM
R1 Replace Gaspack & new Gas pipe
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2007 | ELECTRIC - UFER | JRIVA | Approved | |
| 11/28/2007 | EXCAVATION/LAYOUT REBAR & ZON | JRIVA | Approved | IVRS - Inspection :* |
| 12/05/2007 | STEM WALL/RETAINING WALL | CRUIZ | Approved | IVRS - Inspection :* |
| 12/26/2007 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 12/26/2007 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 12/27/2007 | EXT METAL CLIPS/EXT SHEATHING | CRUIZ | Approved | IVRS - Inspection :* 1) WILL NEED A STRAP ON TOP PLATE ONCE PLUMBING VENT IS INSTALLED-WILL CHECK AT FRAMING |
| 12/27/2007 | U VALUE FOR WINDOW | CRUIZ | Approved | IVRS - Inspection :* |
| 12/31/2007 | STUCCO MESH | RFREIDIN | Approved | IVRS - Inspection :* |
| 01/04/2008 | MECHANICAL - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/04/2008 | ELECTRIC - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/10/2008 | PLUMBING - SEWER HCS CONNECT | CRUIZ | Approved | IVRS - Inspection :* |
| 01/10/2008 | PLUMBING - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection :* |
| 01/10/2008 | PLUMBING - ROUGH, SOIL | CRUIZ | Approved | IVRS - Inspection :* |
| 01/15/2008 | SHEET ROCK NAILING | CRUIZ | Approved | IVRS - Inspection :* |
| 02/01/2008 | PLUMBING - GAS PRESSURE TEST | CRUIZ | Approved | IVRS - Inspection :* |
| 02/20/2008 | MECHANICAL - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 02/20/2008 | PLUMBING - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 02/20/2008 | ELECTRIC - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 02/20/2008 | BUILDING - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
| 02/21/2008 | PERMIT FINALED | JWEATHER | Approved |