Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
6970 S PALO VERDE RD
Apply Date:
11/26/2007
Applicant:
SEAVER FRANKS ARCHITECTS INC AIA
Description:
NEW SHELL BLDG
Architects:
  • SEAVER FRANKS ARCHITECTS INC AIA
Contractors:
  • CHESTNUT CONSTRUCTION CORPORATIO

Permit Reviews

Permit Number - T07CM04449
Permit Status: Final
Permit Description: NEW SHELL BLDG
Start Date Submittal Complete Date Status  
01/25/2008 POST 3RD PARTY REVIEW 02/22/2008 COMPLETED Review Details
03/14/2008 POST 3RD PARTY REVIEW 04/30/2008 COMPLETED Review Details
04/30/2008 RESUBMITTAL 05/07/2008 COMPLETED Review Details
05/07/2008 RESUBMITTAL 09/23/2008 COMPLETED Review Details
09/23/2008 3RD PARTY REVIEW-REVISION/OTHER 09/30/2008 COMPLETED Review Details
10/23/2008 3RD PARTY REVIEW-REVISION/OTHER 10/23/2008 COMPLETED Review Details
11/26/2007 PLANS OK TO SUBMIT - 3RD PARTY 11/26/2007 COMPLETED Review Details
11/26/2007 3RD PARTY REVIEW-COMMERCIAL 01/25/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T07CM04449
Permit Status: Final
Permit Description: NEW SHELL BLDG
Total Outstanding Activity Conditions - 1
Date Name
11/26/2007 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T07CM04449
Permit Description: NEW SHELL BLDG
Total Completed Inspections - 36
Date Description Inspector Results Comments
07/22/2008 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
ABS DWV UNDERGROUND OK TO COVER
WATER TEST OK
07/30/2008 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
08/19/2008 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
1. TEMP POWER TO BE DISCONNECTED FROM GENERATOR AND INSTALLED IN A SAFE MANNER, ASAP - COX. ELEC. CONTR.
2. TEMP CABLE IS SUBJECT TO PHYSICAL DAMAGE
JUST LAYING ON GROUND, ALSO #12 GA. WIRE IS OVERFUSED AT 50 AMP CKT BRKR
3. A STOP WORK ORDER WILL BE ISSUED
IF NOT ADDRESSED 24 HRS.
4. OK 3/0 CU TO 20' REBAR UFER
10/14/2008 FRAMING GDABBS Approved IVRS - Inspection :*
10/14/2008 ROOF NAILING GDABBS Approved IVRS - Inspection :*
10/17/2008 STEM WALL/RETAINING WALL MHENSON Approved IVRS - Inspection :*
1. NORTH RETAINING WALL AND SITE WALLS ON EAST SIDE
2. TERRACON SPECIAL INSPECTED
10/28/2008 PLUMBING - PROGRESS RLEDONNE Approved IVRS - Inspection :*
1. OVERHEAD WATER PIPING INSTALLED PER PLAN TEST OK
2. WATER PIPING IN WALL TO MOP SINK TEST OK
10/28/2008 PLUMBING - YARD WTR LINE/TEST RLEDONNE Approved IVRS - Inspection :*
10/29/2008 ELECTRIC - OUTDOOR LIGHTING DSANTACR Approved IVRS - Inspection :*
OK POLE BASES
11/20/2008 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
CONCRETE MONUMENT SIGN REINFORCEMENT
STEEL OK AS PER DETAIL #3 SHEET #S2.1.1 AND
DETAIL #214 SHEET #S5.0
12/02/2008 ELECTRIC - UNDERGROUND RJIROUDE Approved IVRS - Inspection :*
1. OK 6 - 3" PVC FROM TEP XFMR TO BUILDING
2. OK 6 - 3" PVC FROM TEP XFMR HEADING SOUTHWEST 70' FOR FUTURE BUILDING
12/08/2008 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
OK SOFFITS LTG. ROUGH AT EAST ENTRIES
12/08/2008 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
HOT WATER TO MOP SINK INSULATION OK IN WALL
12/30/2008 BUILDING - PROGRESS GDABBS Approved IVRS - Inspection :*
1) DUMPSTER PADS, TRUCK LOADING AREA AND TRUCK TURN AROUND AT N/W CORNER OK
12/30/2008 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
1) REINFORCEMENT STEEL AT TOW DUMPSTER PADS ON WEST SIDE OF BLDG, TRUCK LOADING DOCK SLAB AT SOUTH END AND TRUCK TURN AROUND AT NORTH/WEST CORNER
02/02/2009 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED FOR "HOUSE METER" PER D. SANTACRUZ
02/10/2009 FIRE - HYDRANTS LTHOMAS Approved
02/10/2009 FIRE SPKLR - FINAL LTHOMAS Approved
02/10/2009 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
02/10/2009 FIRE - FINAL LTHOMAS Approved
02/13/2009 PLUMBING - ROOF DRAINS RLEDONNE Approved
02/13/2009 PLUMBING - SEWER HCS CONNECT RLEDONNE Approved
02/13/2009 PLUMBING - BACK WATER VALVE RLEDONNE Approved
02/13/2009 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
02/17/2009 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved
02/17/2009 ELECTRIC - PROGRESS DSANTACR Approved
02/17/2009 U VALUE FOR WINDOW LHANLY Approved
02/17/2009 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
02/17/2009 OUTDOOR LIGHTING FINAL DSANTACR Approved IVRS - Inspection :*
02/17/2009 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
02/17/2009 SIGN - FINAL JYBARRA Approved
02/17/2009 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
03/26/2009 LANDSCAPE - FINAL PMCLAUGH Approved
04/30/2009 BUILDING - FINAL MHENSON Approved IVRS - Inspection :*
LETTER OF COMPLETION - SHELL
05/04/2009 NPPO - FINAL ACONNOR Approved
06/02/2009 ENGINEERING - FINAL DROBERTS Approved

Documents

File Name Document Type  
001__1 OF 7.TIF CONSTRPLANS VIEW
002__2 OF 7.TIF CONSTRPLANS VIEW
003__3 OF 7.TIF CONSTRPLANS VIEW
004__4 OF 7.TIF CONSTRPLANS VIEW
005__5 OF 7.TIF CONSTRPLANS VIEW
006__6 OF 7.TIF CONSTRPLANS VIEW
007__L1.TIF CONSTRPLANS VIEW
008__7 OF 7.TIF CONSTRPLANS VIEW
009__L2.TIF CONSTRPLANS VIEW
010__L3.TIF CONSTRPLANS VIEW
011__L4.TIF CONSTRPLANS VIEW
012__L5.TIF CONSTRPLANS VIEW
013__L6.TIF CONSTRPLANS VIEW
014__L7.TIF CONSTRPLANS VIEW
015__L8.TIF CONSTRPLANS VIEW
016__L9.TIF CONSTRPLANS VIEW
017__COVER.TIF CONSTRPLANS VIEW
018__A1.1.TIF CONSTRPLANS VIEW
019__A1.2.TIF CONSTRPLANS VIEW
020__1 OF 7.TIF CONSTRPLANS VIEW
021__2 OF 7.TIF CONSTRPLANS VIEW
022__3 OF 7.TIF CONSTRPLANS VIEW
023__4 OF 7.TIF CONSTRPLANS VIEW
024__5 OF 7.TIF CONSTRPLANS VIEW
025__6 OF 7.TIF CONSTRPLANS VIEW
026__7 OF 7.TIF CONSTRPLANS VIEW
027__1 OF 4.TIF CONSTRPLANS VIEW
028__2 OF 4.TIF CONSTRPLANS VIEW
029__3 OF 4.TIF CONSTRPLANS VIEW
030__4 OF 4.TIF CONSTRPLANS VIEW
031__L1.TIF CONSTRPLANS VIEW
032__L2.TIF CONSTRPLANS VIEW
033__L3.TIF CONSTRPLANS VIEW
034__L4.TIF CONSTRPLANS VIEW
035__L5.TIF CONSTRPLANS VIEW
036__L6.TIF CONSTRPLANS VIEW
037__L7.TIF CONSTRPLANS VIEW
038__L8.TIF CONSTRPLANS VIEW
039__L9.TIF CONSTRPLANS VIEW
040__A2.1.TIF CONSTRPLANS VIEW
041__A2.2.TIF CONSTRPLANS VIEW
042__A2.3.TIF CONSTRPLANS VIEW
043__A2.1.TIF CONSTRPLANS VIEW
044__A2.2.TIF CONSTRPLANS VIEW
045__A2.3.TIF CONSTRPLANS VIEW
046__A3.1.TIF CONSTRPLANS VIEW
047__A3.2.TIF CONSTRPLANS VIEW
048__A3.3.TIF CONSTRPLANS VIEW
049__A4.1.TIF CONSTRPLANS VIEW
050__A4.2.TIF CONSTRPLANS VIEW
051__A4.3.TIF CONSTRPLANS VIEW
052__A5.0.TIF CONSTRPLANS VIEW
053__A6.1.TIF CONSTRPLANS VIEW
054__A6.2.TIF CONSTRPLANS VIEW
055__A7.0.TIF CONSTRPLANS VIEW
056__A8.0.TIF CONSTRPLANS VIEW
057__A9.0.TIF CONSTRPLANS VIEW
058__S1.0.TIF CONSTRPLANS VIEW
059__S1.1.TIF CONSTRPLANS VIEW
060__S1.2.TIF CONSTRPLANS VIEW
061__S2.1.1.TIF CONSTRPLANS VIEW
062__S2.1.2.TIF CONSTRPLANS VIEW
063__S2.1.3.TIF CONSTRPLANS VIEW
064__S2.2.1.TIF CONSTRPLANS VIEW
065__S2.2.2.TIF CONSTRPLANS VIEW
066__S2.2.3.TIF CONSTRPLANS VIEW
067__S2.3.1.TIF CONSTRPLANS VIEW
068__S2.3.2.TIF CONSTRPLANS VIEW
069__S2.3.3.TIF CONSTRPLANS VIEW
070__S3.0.TIF CONSTRPLANS VIEW
071__S4.0.TIF CONSTRPLANS VIEW
072__S5.0.TIF CONSTRPLANS VIEW
073__M2.1.TIF CONSTRPLANS VIEW
074__M2.2.TIF CONSTRPLANS VIEW
075__M2.3.TIF CONSTRPLANS VIEW
076__P1.0.TIF CONSTRPLANS VIEW
077__P2.1.TIF CONSTRPLANS VIEW
078__P2.2.TIF CONSTRPLANS VIEW
079__P2.3.TIF CONSTRPLANS VIEW
080__E0.0.TIF CONSTRPLANS VIEW
081__E1.1.TIF CONSTRPLANS VIEW
082__E1.2.TIF CONSTRPLANS VIEW
083__E1.3.TIF CONSTRPLANS VIEW
084__E2.1.TIF CONSTRPLANS VIEW
001__J-1.TIF CONSTRPLANS VIEW
002__J-2.TIF CONSTRPLANS VIEW
STEELJOIST.TIF DOCUMENTS VIEW
STRUCCALCS.TIF DOCUMENTS VIEW
STRUCCALCSSUPPLEMENTAL.TIF DOCUMENTS VIEW
GEOTECHENGRPT.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW