Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2009 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 01/27/2009 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SCREEN WALL FOOTINGS NWC OF BLDG. 1 SPECIAL INSPECTED |
|
| 11/20/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* CONCRETE MONUMENT SIGN REINFORCEMENT STEEL OK AS PER DETAIL #3 SHEET #S2.1.1 AND DETAIL #214 SHEET #S5.0 |
|
| 11/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* NO SUPERINTENDENT ON SITE - DON'T KNOW WHAT TO LOOK AT |
|
| 11/14/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* MONUMENT SIGN FOOTING OK |
|
| 10/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. REMAINING LIGHT POLE CAISSONS 2. SPECIAL INSPECTED |
|
| 10/27/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. 18 CAISSONS AS MARKED ON PLAN 24" X 3/4 BOLTS 2. TERRACON SPECIAL INSPECTED |
|
| 09/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. LOADING DOCK AND NORTH RETAINING WALL FOOTING OK TO POUR 2. TERRACON SPECIAL INSPECTED |
|
| 09/10/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SCREEN WALL FOOTINGS E @ 4.2, 5.2, 6.2 E2 @ 1.2, 2.2, 3.2 1. TERRACON SPECIAL INSPECTED 2. ADD VERTICALS AT CORNER CELLS |
|
| 08/28/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BUILDING #1 REINFORCEMENT STEEL @ TILT PANEL #3 - SPECIAL INSPECTION PERFORMED BY TERRACON/SEAN |
|
| 08/27/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BLDG. #1 REINFORCEMENT STEEL @ TILT UP PANELS #5, 6, 14, 15, 16, 17, 18, 19, 20 AND 21 SPECIAL INSPECTOR TERRACON COMPLETED INSPECTION OK TO POUR |
|
| 08/22/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1. TILT PANELS 1, 2, 4, 7, 8, 9, 10, 11, 12, 13, 14 2. TERRACON SPECIAL INSPECTED 3. PA STRAPS FOR LEDGERS ON SITE TO BE WET SET |
|
| 08/15/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* BLDG. #1 FOOTINGS @ GRID LINES A/1 THRU 7 1/A THRU E, E/1 THRU 7 AND 7/A THRU E - OK TERRACON HAS INSPECTED & APPROVED |
|
| 07/24/2008 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 15 INTERIOR COLUMN FOOTINGS TERRACON SPECIAL INSPECTED LINE 2 - B, C, D LINE 3 - B, C, D LINE 4 - B, C, D LINE 5 - B, C, D LINE 6 - B, C, D |