Permit Details

Status:
Final
Type:
COMMERCIAL ADDITION
Address:
260 S CHURCH AV
Address NEW:
260 S CHURCH AV
Apply Date:
10/12/2007
Applicant:
N/A
Description:
TI: TCC ADA MODIFICATIONS (MUSIC HALL)
Architects:
  • MICKELBERG, PAUL DAVID
Contractors:
  • ENVIRONMENTAL STRATEGIES INC ,

Permit Reviews

Permit Number - T07CM04039
Permit Status: Final
Permit Description: TI: TCC ADA MODIFICATIONS (MUSIC HALL)
Start Date Submittal Complete Date Status  
01/16/2008 RESUBMITTAL 06/18/2008 COMPLETED Review Details
06/18/2008 REVISION - - 1ST 06/24/2008 COMPLETED Review Details
06/24/2008 REVISION - - 1ST 06/24/2008 ACTIVE Review Details
10/12/2007 PLANS OK TO SUBMIT - COMM 10/15/2007 COMPLETED Review Details
10/15/2007 COMMERCIAL TI 12/18/2007 COMPLETED Review Details
12/18/2007 RESUBMITTAL 01/16/2008 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T07CM04039
Permit Status: Final
Permit Description: TI: TCC ADA MODIFICATIONS (MUSIC HALL)
Total Outstanding Activity Conditions - 1
Date Name
10/12/2007 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T07CM04039
Permit Description: TI: TCC ADA MODIFICATIONS (MUSIC HALL)
Total Completed Inspections - 23
Date Description Inspector Results Comments
04/10/2008 NPPO - FINAL ACONNOR Approved N/A
04/10/2008 LANDSCAPE - FINAL ACONNOR Approved N/A
04/10/2008 SIGN - FINAL JYBARRA Approved
04/15/2008 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
05/23/2008 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
OK TO ROCK LID IN RESTROOMS
05/30/2008 PLUMBING - ABOVE CEILING RLEDONNE Approved IVRS - Inspection :*
07/22/2008 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
TR 119 & 120 DWV OK
COPPER OK
SHOWER VALVE NOT YET INSTALLED
RECALL FOR INSP. OF VALVE AND OF SHOWER PAN LINER
07/22/2008 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
08/11/2008 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*
119, 120
08/15/2008 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
OK DRINKING FOUNTAIN ROUGH 1, 2, 3 RD NE SIDE
08/15/2008 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
09/04/2008 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
OK CAN LTG. & DRINKING FOUNTAINS
GREENROOM AND LOBBY
09/11/2008 FRAMING MHENSON Approved IVRS - Inspection :*
WHEELCHAIR PLATFORMS
09/22/2008 BUILDING - PROGRESS MHENSON Approved IVRS - Inspection :*
WHEELCHAIR DECK
SCREWED PER PLAN
09/23/2008 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
ELECTRICAL WORK OR EXCEPT FA NOT COMPLETE
09/26/2008 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
PROVIDE VACUUM BREAKER FOR ALL SHOWER HEADS
02/11/2009 FIRE - FINAL CSCHULTZ Approved
02/11/2009 ENGINEERING - FINAL LHANLY Approved IVRS - Inspection :*
02/11/2009 BUILDING - FINAL LHANLY Approved IVRS - Inspection :*
02/11/2009 PLUMBING - PROGRESS RLEDONNE Approved IVRS - Inspection :*
02/11/2009 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
02/11/2009 ELECTRIC - PROGRESS DSANTACR Approved IVRS - Inspection :*
02/12/2009 PERMIT FINALED BFLORES Approved