Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
10/11/2007
Applicant:
CHAVEZ, MARIO SALAS
Description:
TI:OFFICE
Architects:
  • CHAVEZ, MARIO SALAS

Outstanding Activity Conditions

Permit Number - T07CM04021
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
Date Name
10/11/2007 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T07CM04021
Permit Description: TI:OFFICE
Total Completed Inspections - 22
Date Description Inspector Results Comments
11/26/2007 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
BELOW FLOOR PIPING W/TEST ONE RISER OK
12/13/2007 FRAMING JBURGE Approved IVRS - Inspection :*
OK TO SHEETROCK ONE SIDE
01/09/2008 LANDSCAPE - FINAL ACONNOR Approved N/A
01/09/2008 SIGN - FINAL JYBARRA Approved
01/10/2008 NPPO - FINAL PWHIDDON Approved
01/14/2008 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
01/15/2008 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
01/18/2008 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*
03/07/2008 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
OK FOR CEILING TILES
05/12/2008 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
TILES IN PLACE
T-GRID SYSTEM
05/12/2008 FIRE SPKLR - FINAL LTHOMAS Approved
05/12/2008 FIRE - FINAL LTHOMAS Approved
05/19/2008 TEP CLEARANCE - AM JWEATHER Approved TMPP CLEARED FOR #212 PER R. HOLLANDER
06/03/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
06/05/2008 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
06/05/2008 ELECTRIC - TEMP POWER FOR TEST RHOLLAND Approved IVRS - Inspection :*
06/05/2008 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
06/05/2008 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
06/16/2008 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
09/05/2008 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
TRADES AND FIRE FINALS ARE COMPLETE OK FOR OCCUPANCY
09/24/2009 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
11/05/2009 ENGINEERING - FINAL MRUSSO Approved

Documents

File Name Document Type  
TEMP C OF O_09-17-2008.TIF CERT OF OCC VIEW
None CERT OF OCC VIEW
T07CM04021_001.TIF CONSTRPLANS VIEW
T07CM04021_002.TIF CONSTRPLANS VIEW
T07CM04021_003.TIF CONSTRPLANS VIEW
T07CM04021_004.TIF CONSTRPLANS VIEW
T07CM04021_005.TIF CONSTRPLANS VIEW
T07CM04021_006.TIF CONSTRPLANS VIEW
T07CM04021_007.TIF CONSTRPLANS VIEW
T07CM04021_008.TIF CONSTRPLANS VIEW
T07CM04021_009.TIF CONSTRPLANS VIEW
T07CM04021_010.TIF CONSTRPLANS VIEW
T07CM04021_011.TIF CONSTRPLANS VIEW
T07CM04021_012.TIF CONSTRPLANS VIEW
T07CM04021_013.TIF CONSTRPLANS VIEW
T07CM04021_014.TIF CONSTRPLANS VIEW
T07CM04021_015.TIF CONSTRPLANS VIEW
T07CM04021_016.TIF CONSTRPLANS VIEW
T07CM04021_017.TIF CONSTRPLANS VIEW
T07CM04021_018.TIF CONSTRPLANS VIEW
T07CM04021_019.TIF CONSTRPLANS VIEW
T07CM04021_020.TIF CONSTRPLANS VIEW
T07CM04021_021.TIF CONSTRPLANS VIEW
T07CM04021_022.TIF CONSTRPLANS VIEW
T07CM04021_023.TIF CONSTRPLANS VIEW
T07CM04021_024.TIF CONSTRPLANS VIEW
T07CM04021_025.TIF CONSTRPLANS VIEW
T07CM04021_026.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW