Permit: T07CM03559
Permit Details
Apply Date:
08/29/2007
Applicant:
N/A
Description:
TI: OFFICE
Architects:
- SWAN WAYNE E
Contractors:
- G AND J DEVELOPMENT INC ,
Permit Reviews
Permit Number - T07CM03559
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/29/2007 | COMMERCIAL TI | 08/29/2007 | COMPLETED |
08/29/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/13/2007 | COMPLETED |
09/13/2007 | RESUBMITTAL | 09/13/2007 | COMPLETED |
10/08/2007 | POST 3RD PARTY REVIEW | 10/15/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03559
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/29/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03559
Permit Description: TI: OFFICE
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/17/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
10/10/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES PROVIDE SECONDARY DRAIN FOR FAN COIL WILL CHECK ON FINAL |
10/10/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/10/2007 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
10/10/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
10/10/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
10/10/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
10/10/2007 | FIRE - FINAL | LTHOMAS | Approved | |
10/16/2007 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST DWV OK DEMO CAPS OK WATER PIPING OK 1. SHALL SEE CLOSET FLANGE INSTALL PRIOR TO SETTING STOOL. |
10/17/2007 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* NEW RESTROOM #113 & PLUMBING WALL @ LOUNGE RM #118 AND CORNER WALL @ HALLWAY #115 WEST END |
10/26/2007 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGE OK |
10/29/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
10/29/2007 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
10/30/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
10/30/2007 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
10/30/2007 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
10/30/2007 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
10/30/2007 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
10/30/2007 | ENGINEERING - FINAL | NKALAHAR | Approved | LEFT MESSAGE FOR ERIC AT 955-4506 SPOKE TO JOHN AT 240-8889 DUMPSTER HAS BEEN REMOVED AND NO SITE WORK WAS DONE |
10/31/2007 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
10/31/2007 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
11/01/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved |