Permit: T07CM02906
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
6620 S MEMORIAL PL #100
Address NEW:
6620 S MEMORIAL PL #100
Apply Date:
07/10/2007
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
TI: OFFICE/WAREHOUSE (FOR FURNISHING)
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- BARKER MORRISSEY CONTRACTING INC
Permit Reviews
Permit Number - T07CM02906
Permit Status: C of o
Permit Description: TI: OFFICE/WAREHOUSE (FOR FURNISHING)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/10/2007 | PLANS OK TO SUBMIT - COMM | 07/12/2007 | COMPLETED |
| 07/12/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 08/16/2007 | COMPLETED |
| 08/16/2007 | POST 3RD PARTY REVIEW | 08/21/2007 | COMPLETED |
| 10/16/2007 | POST 3RD PARTY REVIEW | 10/17/2007 | COMPLETED |
| 11/07/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 11/07/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM02906
Permit Status: C of o
Permit Description: TI: OFFICE/WAREHOUSE (FOR FURNISHING)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/10/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM02906
Permit Description: TI: OFFICE/WAREHOUSE (FOR FURNISHING)
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/24/2007 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* RECEIVED LETTER FOR OK OF PVC CELLULAR CORE DWV PIPING |
| 08/30/2007 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* PLUMBING INFILL TRENCHES & 2 HOUSEKEEPING PADS ON NORTH |
| 09/24/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK TO SHEETROCK HARD LIDS |
| 09/24/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* ROOMS #104, 105, 106 |
| 10/05/2007 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* ROOMS #104, 105, 106, 128 & 127, 101, 100 |
| 10/17/2007 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
| 10/17/2007 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
| 10/22/2007 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* WALK IN REFER SLAB |
| 10/23/2007 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 11/01/2007 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/02/2007 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* OK HARD LID ELECTRIC CLOSET |
| 11/07/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED FOR #100 PER R. JIROUDEK |
| 11/07/2007 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* 1) THIS PARTIAL APPROVAL PENDING REVISED SET OF PLANS 2) NEED TO PROVIDE LETTER OF TORQUE FOR TERMINATIONS 3) RECEIVED CHECK #1181 FOR $150 FROM BARKER MORRISSEY FOR AFTER HOURS INSPECTION ON SERVICE |
| 11/07/2007 | ELECTRIC - RECONNECT | RJIROUDE | Approved | IVRS - Inspection :* |
| 11/08/2007 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 11/09/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 11/09/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 11/09/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 11/09/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 11/09/2007 | SIGN - FINAL | JSONKN | Approved | |
| 11/26/2007 | ENGINEERING - FINAL | DROBERTS | Approved | TEMPORARY C OF O APPROVAL AT THIS TIME, FINAL NOT TO BE GIVEN UNTIL ALL OF THE WORK HAS BEEN COMPLETED ON THE EXTERIOR PARKING LOT. IT WAS NOTED DURING THE SITE VISIT THAT THE REQUIRED BICYCLE RACK HAS NOT YET BEEN INSTALLED, AND THAT AN EXISTING HANDICAP PARKING SPOT REMAINS IN AN AREA THAT IS NOT ACCESSABLE. THE DEVELOPER WILL HAVE THESE ISSUES CORRECTED BEFORE HE SCHEDULES A FINAL INSPECTION. |
| 11/26/2007 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 11/27/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) AIR BALANCE OK 2) TESTED DUCT SMOKE DETECTORS 3) OK FOR FINAL |
| 11/27/2007 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* |
| 11/27/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 11/28/2007 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* OK TO APPLY FOR TEMP C OF O PENDING APPROVAL OF TRADE FINALS - NO LIFE SAFETY ISSUES RE: BUILDING |
| 11/28/2007 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* 1. COMPLETE ITEM #1 FROM INSPECTION ON 11/09/07 2. ALL OTHER PREVIOUS INSPECTION ITEMS CORRECTED 3. RECALL WHEN EQUIPMENT INSTALLED |
| 11/28/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 11/30/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* RECEIVED (2) IN HOUSE BACKFLOW CERTIFICATIONS, BACTERIA REPORT TO BE TURNED IN AT FINAL INSPECTION APPROVAL AND COMPLETE ALL PLUMBING INSTALLS |
| 07/31/2008 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/31/2008 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/31/2008 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/25/2008 | PLUMBING - MEDICAL GAS/FINAL | RRICH | Approved | IVRS - Inspection :* |
| 09/04/2008 | PERMIT FINALED | LJACKSON | Approved |