Permit: T07CM01916
Permit Details
Apply Date:
05/08/2007
Applicant:
MIREK EDWARD
Description:
ADDT: GARAGE AND CONVERT CARPORT TO DEN R1 Truss Design
Permit Reviews
Permit Number - T07CM01916
Permit Status: Final
Permit Description: ADDT: GARAGE AND CONVERT CARPORT TO DEN
R1 Truss Design
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/13/2007 | PLANS OK TO SUBMIT - RES | 07/13/2007 | COMPLETED |
| 07/13/2007 | RESUBMITTAL | 07/31/2007 | COMPLETED |
| 08/14/2007 | RESUBMITTAL | 10/11/2007 | COMPLETED |
| 10/11/2007 | REVISION - - 1ST | 10/11/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01916
Permit Status: Final
Permit Description: ADDT: GARAGE AND CONVERT CARPORT TO DEN
R1 Truss Design
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/08/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM01916
Permit Description: ADDT: GARAGE AND CONVERT CARPORT TO DEN
R1 Truss Design
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/24/2007 | ELECTRIC - UFER | DQUINN | Approved | |
| 10/24/2007 | BUILDING PRE-SLAB | DQUINN | Approved | IVRS - Inspection :* |
| 10/24/2007 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | IVRS - Inspection :* |
| 11/13/2007 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 11/13/2007 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | U VALUE FOR WINDOW | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | STUCCO MESH | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 11/16/2007 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
| 11/21/2007 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 12/18/2007 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | IVRS - Inspection :* |
| 12/18/2007 | MECHANICAL - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 12/18/2007 | PLUMBING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 12/18/2007 | ELECTRIC - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 12/18/2007 | BUILDING - FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 12/19/2007 | PERMIT FINALED | JWEATHER | Approved |