Permit: T07CM00998
Permit Details
Apply Date:
03/12/2007
Applicant:
N/A
Description:
NEW SHELL GRANT ROAD PROFESSIONAL PLAZA BLDG # 1
Contractors:
- R AND L BUILDERS L L C
Permit Reviews
Permit Number - T07CM00998
Permit Status: Final
Permit Description: NEW SHELL GRANT ROAD PROFESSIONAL PLAZA BLDG # 1
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/12/2007 | PLANS OK TO SUBMIT - SITE | 06/26/2007 | COMPLETED |
03/12/2007 | PLANS OK TO SUBMIT - COMM | 03/12/2007 | COMPLETED |
03/20/2007 | COMMERCIAL NEW | 05/16/2007 | COMPLETED |
06/22/2007 | RESUBMITTAL | 08/06/2007 | COMPLETED |
06/26/2007 | SITE | 07/09/2007 | COMPLETED |
07/09/2007 | RESUBMITTAL - SITE | 07/09/2007 | COMPLETED |
08/06/2007 | RESUBMITTAL | 08/24/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM00998
Permit Status: Final
Permit Description: NEW SHELL GRANT ROAD PROFESSIONAL PLAZA BLDG # 1
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/12/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM00998
Permit Description: NEW SHELL GRANT ROAD PROFESSIONAL PLAZA BLDG # 1
Total Completed Inspections - 49
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/15/2007 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CONTRACTOR CANCELLED |
06/24/2008 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* OK TO COVER. USE CLEAN FILL W/NO ROCKS UPC REQUIRES HAND FILL TO 12" |
07/16/2008 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR SLAB |
07/16/2008 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
07/16/2008 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
08/20/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN |
09/04/2008 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO MESH EXTERIOR WALLS |
09/09/2008 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO EXTERIOR WALLS |
09/16/2008 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* INSTALL MISSING SUPPORT |
10/17/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* OK WATER PIPE BOND |
11/10/2008 | MECHANICAL - UNDERGROUND | MRAMBER | Approved | |
11/10/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | |
11/10/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
11/10/2008 | MECHANICAL - PROGRESS | MRAMBER | Approved | |
11/10/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
11/13/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
11/18/2008 | RIGHT OF WAY - FINAL | THARVISO | Approved | |
11/18/2008 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | |
11/18/2008 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | |
11/18/2008 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | |
11/18/2008 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
11/18/2008 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
11/18/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
11/18/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
11/18/2008 | ZONING - FINAL | ACONNOR | Approved | |
11/18/2008 | NPPO - FINAL | ACONNOR | Approved | |
11/18/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
11/21/2008 | ENGINEERING - FINAL | JBRUCKME | Approved | REVISED AND C.O.T. APPROVED GRADING PLAN IS REQUIRED FOR ALL ADDITIONAL C OF O'S FOR THIS PROJECT. |
12/23/2008 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | |
12/23/2008 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | |
12/23/2008 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | |
12/23/2008 | ELECTRIC - TEMPORARY SERVICE | RMORENO | Approved | |
12/23/2008 | ELECTRIC - CABLE DROP | RMORENO | Approved | |
12/23/2008 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | |
12/23/2008 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | |
12/23/2008 | ELECTRIC - UNDERGROUND | RMORENO | Approved | |
12/23/2008 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
12/23/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
12/23/2008 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
12/23/2008 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
12/23/2008 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
12/23/2008 | FIRE - FINAL | LTHOMAS | Approved | |
12/23/2008 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |