Permit: T07CM00653
Permit Details
Apply Date:
02/16/2007
Applicant:
ERIC GRIGEL M3 INGINEERING
Description:
NEW WAREHOUSE BUILDING: # 2
Architects:
- MULLIGAN, DENNIS MYLES
Contractors:
- LANG WYATT CONSTRUCTION ,
Permit Reviews
Permit Number - T07CM00653
Permit Status: C of o
Permit Description: NEW WAREHOUSE
BUILDING: # 2
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/15/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 02/20/2008 | COMPLETED |
02/16/2007 | PLANS OK TO SUBMIT - COMM | 02/16/2007 | COMPLETED |
02/16/2007 | 3RD PARTY REVIEW-COMMERCIAL | 04/17/2007 | COMPLETED |
04/17/2007 | POST 3RD PARTY REVIEW | 06/06/2007 | COMPLETED |
06/21/2007 | RESUBMITTAL | 07/31/2007 | COMPLETED |
08/06/2008 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 10/15/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM00653
Permit Status: C of o
Permit Description: NEW WAREHOUSE
BUILDING: # 2
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/16/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM00653
Permit Description: NEW WAREHOUSE
BUILDING: # 2
Total Completed Inspections - 36
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/26/2008 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* PARTIAL WAREHOUSE BUILDING SLAB NOT DOCK LIFT |
05/15/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
07/08/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* 18" FINISH WALL TO CENTER OF TOILET |
08/13/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
08/13/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
09/04/2008 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* |
10/17/2008 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* APPROVED PER APPROVED PLANS |
10/20/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
10/23/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
10/23/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
10/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* |
11/17/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
11/17/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
11/17/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
11/21/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
11/21/2008 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
11/21/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
11/21/2008 | FIRE - FINAL | LTHOMAS | Approved | |
11/28/2008 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
11/28/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
11/28/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
11/28/2008 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
12/03/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
12/03/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
12/03/2008 | NPPO - FINAL | ACONNOR | Approved | N/A |
12/03/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
12/03/2008 | SIGN - FINAL | JYBARRA | Approved | |
12/04/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1. PROVIDE AIR BALANCE REPORT 2. NO LIFE SAFETY ISSUES OBSERVED 3. DUCT SMOKE DETECTOR TEST OK 4. SEE BUILDING INSPECTOR FOR TEMP C OF O |
12/04/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
12/05/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* OK FOR TEMP C OF O FIRE APPROVED COMMUNICATED WITH TRADES |
12/05/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* 1. PROVIDE CLEANOUT AT SINK IN BREAKROOM 2. COMPLETE TRIM FOR CLEANOUT AT WAREHOUSE SINK 3. COMPLETE COOLER DRAIN CLEANOUTS UNCOVER & COMPLETE ALL CLEANOUT 4. PAINT ALL VENT ON ROOF 5. CLEAN WATER REPORT ON SITE |
12/05/2008 | ENGINEERING - FINAL | MAVERY | Approved | OK for temp C of O. Contractor needs to: 1- Separate all construction activity, materials and debris from public access. 2- Clean all wash out from around building. 3- Install safety barriers as-needed around all open holes and work activity. |
12/12/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* FINISH LIGHT POLES AND X-FORMER 3R COVERS |
02/02/2009 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
02/02/2009 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
05/19/2009 | PERMIT FINALED | LJACKSON | Approved |