Permit: T07CM00653

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
10/23/2008 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
10/10/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SPECIAL INSPECTION APPROVED
SOUTH WAREHOUSE LOADING DOCK REINFORCEMENT STEEL
06/26/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. DOCK LIFT OK TO POUR
2. CURB ANGLE TO BE POURED IN SIDEWALK POUR
03/31/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
DONE PER PLAN (REBAR)
02/26/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PARTIAL WAREHOUSE FOOTINGS NOT DOCK LIFT
01/15/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PARTIAL COLUMNS F/1.3, 1.5, 1.8, 2, 2.2, 2.5 -- OK TO POUR

TERRACON SPECIAL INSP. S.ALBA
01/09/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
RECALL WHEN TUBES SET
ADD #3 RING NOT SPACED PER PLAN
TERRACON SPECIAL R. STEPHENSON

COLUMN F/1.3, F/1.5, F/1.8, F/2, F/2.2, F/2.5
01/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
TERRACON SPECIAL R.STEPHENSON

F-1.3, F-1.5, F-1.8, F-2, F-2.5, D-2.5 COLUMN FOOTINGS
01/03/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
SPREAD FOOTINGS @ GRID 2/A-B-C-D - 3/A-B-C-D - 1/A-B-C-D-E
2.6/E - TOTAL OF 14 AND E/1.3- 1.6 - 1.8 - 2 - 2.2
AND A/1.3 - 1.6 - 2.3 - 2.6