Permit: T07CM00273
Permit Details
Apply Date:
01/23/2007
Applicant:
N/A
Description:
NEW OFFICE LOT# 27
Contractors:
- VENTURE WEST INC *C
Permit Reviews
Permit Number - T07CM00273
Permit Status: C of o
Permit Description: NEW OFFICE
LOT# 27
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/23/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 01/30/2007 | COMPLETED |
01/30/2007 | 3RD PARTY REVIEW-COMMERCIAL | 03/09/2007 | COMPLETED |
03/09/2007 | POST 3RD PARTY REVIEW | 07/24/2007 | COMPLETED |
08/02/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 08/09/2007 | COMPLETED |
08/07/2007 | 3RD PARTY REVIEW-REVISION/OTHER-2ND | 08/09/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM00273
Permit Status: C of o
Permit Description: NEW OFFICE
LOT# 27
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/23/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM00273
Permit Description: NEW OFFICE
LOT# 27
Total Completed Inspections - 42
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/18/2007 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
04/18/2007 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
05/08/2007 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR |
05/08/2007 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* ENSURE THE REMOVAL OF ALL TRASH & DEBRIS ALL REBAR IS 3" OFF THE GROUND -- OK TO POUR |
05/08/2007 | PLUMBING - PRE SLAB | BBENEDON | Approved | IVRS - Inspection :* |
06/25/2007 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN |
06/25/2007 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO MESH |
07/17/2007 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2007 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
07/17/2007 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
07/19/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUPPLY & EXHAUST IN RESTROOM OK FOR SHEETROCK CONDENSATE DRAINS OK STAT WIRE IN WALL OK |
07/19/2007 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO |
07/19/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK ROUGH |
07/24/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* SOFFITS & RECEPTION AREA COMPLETE -- OK TO SHEETROCK |
07/30/2007 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
08/22/2007 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
08/22/2007 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* OK TO SET TILES |
08/22/2007 | PLUMBING - MEDICAL GAS/TEST | RRICH | Approved | IVRS - Inspection :* |
09/26/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
10/01/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
10/01/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/01/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
10/01/2007 | PLUMBING - MEDICAL GAS/FINAL | BBENEDON | Approved | IVRS - Inspection :* |
10/01/2007 | PLUMBING - MD GAS/PRECONST MTG | BBENEDON | Approved | IVRS - Inspection :* |
10/01/2007 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
10/01/2007 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
10/02/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
10/02/2007 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
10/02/2007 | NPPO - FINAL | ACONNOR | Approved | |
10/02/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
10/03/2007 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
10/03/2007 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
10/03/2007 | FIRE - FINAL | LTHOMAS | Approved | |
10/04/2007 | MECHANICAL - FINAL | JMILITEL | Approved | |
10/04/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
10/04/2007 | ENGINEERING - FINAL | JBRUCKME | Approved |